#* Technical Specifications | #* Technical Specifications | ||
# Tagging Spectrometer | # Tagging Spectrometer | ||
− | #* [http://www.jlab.org/~jstewart/ | + | #* [http://www.jlab.org/~jstewart/Optics_1085_v4.doc Optics calculations for the Hall D tagging spectromter magnet for a 12 GeV electron beam - G. Yang 2008 ed. D Sober] |
#* [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1085 Optics calculation for a single magnet tagger spectrometer - G. Yang 2008] | #* [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=1085 Optics calculation for a single magnet tagger spectrometer - G. Yang 2008] | ||
#* [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=588 Stress Analysis for the Hall D Tagger - G. Yang] | #* [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=588 Stress Analysis for the Hall D Tagger - G. Yang] |
Revision as of 21:05, 4 November 2008
Contents
The Hall D/GlueX Tagger and Beamline Review
- Agenda
- Charge
- November 19-20 Review Website (halld guest)
- Previous Reviews
Material Prepared for the Review
- Pre-brief Material for the reviewers
- General Documents
- GlueX-doc-1063 GlueX Physics and Detector Performance Metrics
- Technical Design of the Hall D Polarized Photon Beam
- Technical Specifications
- Tagging Spectrometer
- Electron Machine
- Tagger Hall Song Sheet
- Machine interface Document
- Shielding Basis for Hall D Complex
- (Document included as supplimental information. Not part of this review.)
- Fixed Hodoscope
- The microscope detector
- Pair Spectrometer
- Plan for what we want to study with diamonds.
- Simulations of collimatior cave and pair spectrometer background- Alex
- Trigger rates and background - Alex
- Final Talks
- GlueX-doc-1xxx GTemplate
Relevant Wiki Pages
- Description Photon Beam
- Biweekly Meetings
- Drawings (Tim)
Dry Run Schedule for the Review
First round of dry runs (week of November 3rd)
Thursday, November 6, 2008 Room F326/327
- 9:00-10:30--- Photon Beam Overview--- R. Jones
- 10:30-12:00--- Beam Simulations--- A. Somov
- 2:15-3:30--- Pair Spectrometer --- J. Stewart
- 3:30-4:30--- Microscope--- I. Senderovich
- 4:30-5:30--- Tagger Optics--- D. Sober
Friday, November 7, 2008 Room F326/327 and L207
- 9:00-10:30 (L207) Diamond Selection and Testing--- R. Jones
- 10:30-12:00 (L207) Photon Beam Line--- T. Whitlatch
- 2:15-4:00 (F326/327) Fixed Array Hodoscope--- F. Klein
Monday, November 10, 2008 Room F326/327
- 9:00-10:30--- Magnet Design--- J. Stewart
- 1:00-2:30--- 12 GeV Electron Beam--- Y. Roblin
Richard not available 12:00 - 14:00
Second round of dry runs (week of November 10)
Tuesday, November 11, 2008 Room F326/327
- 1:00-2:30--- Beam Simulations--- A. Somov
Wednesday, November 12, 2008 Room F326/327
- 9:00-10:30--- 12 GeV Electron Beam--- Y. Roblin
- 3:30-5:00--- Photon Beam Overview--- R. Jones
Thursday, November 13, 2008 Room F326/327
- 8:00-9:00--- Microscope--- I. Senderovich
- 9:00-10:00--- Tagger Optics--- D. Sober
- 10:00-11:30--- Magnet Design--- J. Stewart
- 3:00-4:30--- Diamond Selection and Testing--- R. Jones
Friday, November 14, 2008 Room F326/327
- 8:00-9:00--- Overview of Hall D Detector--- E. C. Aschenauer
- 9:00-10:30--- Photon Beam Line--- T. Whitlatch
- 10:30-12:00--- Fixed Array Hodoscope--- F. Klein
- 2:30-4:00--- Pair Spectrometer--- J. Stewart
Main Review
- Review: November 19 and 20.
- issues that need special attention