Difference between revisions of "JEF meeting, August 19, 2022"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 7: | Line 7: | ||
* Simulations/Analysis | * Simulations/Analysis | ||
* Preparation of parts for FCAL2 modules -- Sasha | * Preparation of parts for FCAL2 modules -- Sasha | ||
− | + | ** [https://halldweb.jlab.org/wiki/index.php/CRYTUR Discuss possibility to order 20 more CRYTUR crystals during this F.Y. | |
− | ** [https://halldweb.jlab.org/wiki/index.php/CRYTUR | + | Have already received 5 more crystals from physics division]. |
− | ** Meeting with the DSG group | + | ** Meeting with the DSG group: Mindy and George will continue working on the project in September |
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg] | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/part_preparation.pdf Preparation of parts][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students1.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students2.jpg][https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/6_17_22/students3.jpg] | ||
− | *** | + | *** Need: 300 brass assemblies (Keith and Chris will continue to work on them. Waiting for straps) |
− | + | *** Expect to receive remaining 200 light guides during a couple of next weeks. | |
− | *** | + | *** Need about 400 PMT housing |
− | *** | + | |
− | + | ||
− | + | ||
− | + | ||
** Task for the next week: Perform inventory of all fabricated crystals. Prepare to move to the new lab. | ** Task for the next week: Perform inventory of all fabricated crystals. Prepare to move to the new lab. | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 684 | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals:] 684 |
Revision as of 23:04, 18 August 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- [https://halldweb.jlab.org/wiki/index.php/CRYTUR Discuss possibility to order 20 more CRYTUR crystals during this F.Y.
Have already received 5 more crystals from physics division].
- Meeting with the DSG group: Mindy and George will continue working on the project in September
- Preparation of parts[1][2][3]
- Need: 300 brass assemblies (Keith and Chris will continue to work on them. Waiting for straps)
- Expect to receive remaining 200 light guides during a couple of next weeks.
- Need about 400 PMT housing
- Task for the next week: Perform inventory of all fabricated crystals. Prepare to move to the new lab.
- Wrapped CRYTUR crystals: 684
- All currently available (consider to borrow some spares from NPS)
- Module fabrication -- Sasha
- Received 85 PMT housings from Tim, they have been honed by Bobby. All of them will be used today.
- Status of fabrication
- Fabricated modules: Total 1153
- All SICCAS 577 SICCAS
- 576 CRYTUR, Remaining: 121
- Clean room EEL126 [4][5]
- Expect to move to the new lab EEL108 (the same building) [6]
- Work on amending safety docs
- Module fabrication -- Sasha
- Light Monitoring System -- Arshak