Difference between revisions of "JEF meeting, March 17, 2023"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 24: | Line 24: | ||
* '''[[Testing of PMT dividers]]''' -- Sasha / Arshak | * '''[[Testing of PMT dividers]]''' -- Sasha / Arshak | ||
** FCAL2 modules with dividers installed on the CCAL [https://logbooks.jlab.org/entry/4140983] | ** FCAL2 modules with dividers installed on the CCAL [https://logbooks.jlab.org/entry/4140983] | ||
− | * '''Installation of the FCAL2 detector''' -- Sasha / Arshak | + | * '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak |
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
− | |||
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | ** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings] | ||
** Manpower and division of tasks | ** Manpower and division of tasks |
Revision as of 09:21, 17 March 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Available crystals:
- 1450 (modules)
- 32 (ready for fabrication)
- 40 (installed on CCAL) available on March 20
- (some CCAL crystals from the inner part will not be used for the FCAL2)
- 95 expect to receive from CRYTUR in May [1]
- Total 1617
- George (DSG group) finished with disassembling CCAL modules and removing LMS caps. Will work on preshaping ESR reflectors for CRYTUR. The oven will be ready in a week.
- Mindy (DSG group) solder wires to sockets (while waiting for crystals). More crystals will come from the CCAL during next week.
- Available crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1470 (15 modules fabricated since last week)
- Currently available for fabrication: 12
- Fabricated modules: Total 1470 (15 modules fabricated since last week)
- Testing of PMT dividers -- Sasha / Arshak
- FCAL2 modules with dividers installed on the CCAL [2]
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [3]
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light Monitoring System -- Arshak
- Simulations/Analysis