Line 10: |
Line 10: |
| * Discuss crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha | | * Discuss crystal module install, shimming etc... [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation] - Sasha |
| * Cable update [[Media:FCAL2_lv,board.pdf]] | | * Cable update [[Media:FCAL2_lv,board.pdf]] |
− |
| |
− | == Minutes ==
| |
− | * Discussed minutes from last meeting
| |
− | ** what inspections/marking/labeling are needed prior to removal of lead glass blocks?
| |
− | *** Malte to come up with a written procedure of what they plan on
| |
− | *** Need for good tracking of all modules
| |
− | *** There will be several surveys and measurements for baseline
| |
− | *** Sasha wants to minimize rewrapping - needs to come up with a threshold
| |
− | *** Malte and Mark Dalton wish to be involved in FCAL module dis-assy
| |
− | * Going through new version of Gant chart
| |
− | ** Matt commented on the fact that some dates do not make sense
| |
− | ** Need to update Gant chart with more realistic time frames
| |
− | ** Need to tie Sasha's manpower chart into Gant
| |
− | ** Malte making base stress test plan to determine weak base
| |
− | *** to be done in January
| |
− | *** prepare stock pile of new bases
| |
− | * Discussed need for written procedures for all aspects of the project
| |
− | ** Sasha wishes to be responsible for all procedures pertaing to lead glass and crystal modules
| |
− | ** He may need some help? Who will do what - This needs to be decided in order for things to go smoothly
| |
− | * Discussed desire to downgrade Hall for GERT only, can ESB be downgraded?
| |
− | * Discussed the need for a planned quantity of modules to be re-wrapped
| |
− | ** This will be based on Sasha's proposed student manpower for 3 months
| |
− | ** 700 modules to be re-wrapped is the current baseline
| |
− | ** Sasha will obtain materials for many more just in case
| |
− | * Discussed cables
| |
− | ** Sasha Fernando proposed a change to put PCBs at chains for LV
| |
− | *** Proposed horizontal layout will be too crowded
| |
− | *** Will meet in a separate meeting again to decide on this
| |
− | * Sasha showed a working layout for tables and shelving in hall for lead glass and crystal modules
| |
− | ** Concern with stability of free standing shelving
| |
− | ** Can tie 2 shelves together for stability
| |
− | ** Modify existing wall shelving for length of lead glass modules
| |
− | ** Need to determine how much existing shelving and what is needed to procure
| |
− | * Discussed rack and crate layout
| |
− | ** Sasha showed his proposed crate layout
| |
− | ** Need to strategically place racks for simplified cable paths
| |
− | ** Show 3d model of rack layout next meeting
| |
− | * Discussed need for mock ups
| |
− | ** Maybe use ComCal as a mock up for new cabling in January when it is removed from the hall
| |
− | ** Use lead glass to verify all wrapping /rework procedure so traing can be done well for students
| |
− | ** Use videos to teach students?
| |
− | * Discussed use of 2 scissor lifts instead of big platform upstream of the FCAL
| |
− | ** Need to demonstrate stability of lift at heights
| |
− | ** Rent 2nd larger lift with 4 ft extension ($1K / month)
| |
Wednesday March 12, 2023 9am
At Jefferson Lab, Hall D Counting House and on Zoom