** - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left  
 
** - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left  
 
** - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
** - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
::# - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
+
::  - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
::# - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
+
::  - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
 
** - Fix front panel of two LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg]
 
** - Fix front panel of two LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg]
 
:::  - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
 
:::  - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables

Revision as of 08:43, 6 September 2024

Meeting time and location:

Agenda

  • Preparation of parts for ECAL -- Sasha
    • - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left
    • - HV distribution boards [1][2]
- 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
    • - Fix front panel of two LV distribution boards [3]
- new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
    • - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
  • Installation and testing dividers has been completed [4]
- need to arrange cables on chains
- need to arrange cables on cable trays
  • Students -- Sasha
    • - Expect one student from Wuhan, waiting for the US visa
  • Beam tests with the PS
      • measure shower beam profile and reconstruction in the crystal/LG transition region
      • (install prototype with 5x5 PbWO4 modules + ? LG)
  • Other hardware projects
    • prototype of the ECAL veto counter (?)
  • Analysis/Simulation