* Notes:
 
* Notes:
** Area is in the test lab, footprint 20'6" x 25'9", currently filled with coils and coil parts.
+
** Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
 
** May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
 
** May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
** Need space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
+
** May need extra space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
** Must maintain clear areas around racks, power supply and cannot block pedestrian areas.
+
** Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
** Platform is 172" x 160".
+
** Platform is 172" x 160", cryo can will sit on top.
** Need to design piping to vent N2.
+
** Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
** Need to design piping for warm and cold He, LN2.
+
** Need come-alongs and anchors to move yokes and coils along rails.
  
 
* To Do:
 
* To Do:
Line 20: Line 20:
 
** Arrange for piping designer - George
 
** Arrange for piping designer - George
 
** Investigate sensitivity of electronic equipment to B fields - Elliott
 
** Investigate sensitivity of electronic equipment to B fields - Elliott
 +
** Dsign piping to vent N2 - ?
 +
** Design warm and cold He supply/return systems, and LN2 supply system - ?
  
  
Line 25: Line 27:
 
** Verify we can borrow heat exchanger from Hall A - George
 
** Verify we can borrow heat exchanger from Hall A - George
 
** Order warm He and N2 piping - ?
 
** Order warm He and N2 piping - ?
 +
** Retrieve rails from IU - ?
  
  

Revision as of 13:56, 18 June 2009

Notes and to-do lists for the solenoid coil tests this summer and fall.


Test Area

  • Notes:
    • Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
    • May be able to get space in adjacent area (QWeak construction and SRF cavity storage areas).
    • May need extra space for large power supply (6' x 5') and to avoid placing controls racks in large B field.
    • Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
    • Platform is 172" x 160", cryo can will sit on top.
    • Area has two cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
    • Need come-alongs and anchors to move yokes and coils along rails.
  • To Do:
    • Look into getting space in adjacent areas - George
    • Look into possibility of locating computer in control room - Elliott
    • Distribute Floyd's B field map for single coil, no cladding - George
    • Determine location of all components - Wayne
    • Arrange for piping designer - George
    • Investigate sensitivity of electronic equipment to B fields - Elliott
    • Dsign piping to vent N2 - ?
    • Design warm and cold He supply/return systems, and LN2 supply system - ?


    • Verify we have all cryo transfer lines and U-tubes - Mark S
    • Verify we can borrow heat exchanger from Hall A - George
    • Order warm He and N2 piping - ?
    • Retrieve rails from IU - ?


Infrastructure

  • Notes:
  • To Do:


Components

  • Notes:
  • To Do:


Staging

  • Notes:
  • To Do:


Reviews

  • Notes:
    • Micro-review of PLC vendor choice completed, waiting for report.
  • To Do:
    • Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review.