* [http://www.jlab.org/~whitey/Hall_D/TAGGER/QP_mag_sht1.pdf Tagger hall Quad magnet sht 1] | * [http://www.jlab.org/~whitey/Hall_D/TAGGER/QP_mag_sht1.pdf Tagger hall Quad magnet sht 1] | ||
* [http://www.jlab.org/~whitey/Hall_D/TAGGER/QP_mag_sht2.pdf Tagger hall Quad magnet sht 2] | * [http://www.jlab.org/~whitey/Hall_D/TAGGER/QP_mag_sht2.pdf Tagger hall Quad magnet sht 2] | ||
+ | * [[Preliminary drawing by Yang]] | ||
+ | * [[35% drawing by IHEP provided in April/May 2007]] | ||
+ | ** [[Private: Suggestion on changes to the 35% drawings]] | ||
+ | * [[Statement of Work for the 100% engineering drawings]] | ||
+ | ** [[Private: Discussion of the Statement of Work]] | ||
+ | * [[Media:TAGGERINTERface.pdf | Tagger interface drawing]] | ||
+ | * [[Standard Beamline Quadrupole Specification]] | ||
+ | * [[Media:Prelim_tagger_dwgs.pdf | Tagger Preliminary drawings 10May10]] | ||
+ | * [[Media:Prelim_Hall-D_Tagger_Dipole_Magnet_Specification_4-30-2010.doc | Tagger magnet prelim spec May 2010]] | ||
+ | |||
==Broadband Tagger Hodoscope== | ==Broadband Tagger Hodoscope== | ||
* 35% drawings produced by Catholic Univ. ''(5/2007)'' | * 35% drawings produced by Catholic Univ. ''(5/2007)'' |
Revision as of 14:27, 1 June 2010
Contents
Tagging Spectrometer
- Conceptual drawings produced by the Glasgow group (ca. 2006)
- 35% drawings produced by the IHEP group (5/2007)
- Interface drawings produced at JLab (1/2008)
- Tagger magnet and chamber section 1 July, 30, 2008 - July 30, 2008
- Tagger magnet and chamber section 2 July, 30, 2008 - July 30, 2008
- Tagger magnet Cross section from Yang Tosca Sept 10, 2008
- Tagger magnet modified Cross section from Yang Tosca Sept 26, 2008
- Tagger magnet critical interfaces Sht 2 Feb 23, 2009
- Tagger magnet critical interfaces sht 1 FEB 23, 2009
- Tagger hall Quad magnet sht 1
- Tagger hall Quad magnet sht 2
- Preliminary drawing by Yang
- 35% drawing by IHEP provided in April/May 2007
- Statement of Work for the 100% engineering drawings
- Tagger interface drawing
- Standard Beamline Quadrupole Specification
- Tagger Preliminary drawings 10May10
- Tagger magnet prelim spec May 2010
Broadband Tagger Hodoscope
- 35% drawings produced by Catholic Univ. (5/2007)
Tagger Microscope
Active Collimator
- 100% drawings produced by Univ. of Connecticut (6/2006)
Tagger Hall
- Civil design produced by engineering firm for JLab (10/2007)
Collimator Cave
- Conceptual design of shielding plan from Connecticut (5/2006)
- Civil design produced by engineering firm for JLab (10/2007)
- Collimator Cave Layout Aug 20, 2008 - Aug 20, 2008
- Collimator Cave Isometric Jul 18, 2008 - July 18, 2008