Solenoid Coil Test Weekly Meeting
Location and Time
- Fri 1-Apr-2011 9:30 am ARC 231
NOTE: we are back to ARC 231 again, hopefully for good!
Agenda
- Coil 3 installation status
- Improvements needed for coil 3
- Hi-pot testing and short to ground, max voltage, center tap, etc.
- Danfysik power transistor
- balancing quench detector given new inductance calculation and tap locations
- document trip chains
- trip sequence diagnosis system
- slow dump still not working
- new wiring
- PLC system improvements
- additional licenses and modules
- New VME-based fast DAQ system
- hardware, software, commissioning status
- Other testing with coil 3
- VXS/VME crates in B field
- other tests?
- To-do list for the next coil
- measure UPS lifetime under operating conditions
- Coil 2 repair status
- IRMIS
- Preparing for moving into the hall