− | Attendees: Elliott W, Dave A, Chris C, Fernando B, Mark I, Elton S, Dave D, Ed J, Carl T, Simon T | + | Attendees: Elliott W, Dave A, Chris C, Fernando B, Mark I, Elton S, Dave D, Ed J, Carl T, Simon T. |
'''Chris Cuevas gave an update on electronics:''' | '''Chris Cuevas gave an update on electronics:''' | ||
+ | |||
+ | * Many specs and drawings in draft state, prototypes are coming. | ||
+ | * Manpower is a big problem given deadlines, esp. for the crate-sum module. | ||
+ | * Two more 20-slot VXS crates on order. | ||
+ | * Slightly behind on FADC October milestones, no full crate tests yet. | ||
+ | * Hai will work on FADC after completing an Accelerator project. | ||
+ | * New hire will arrive in Jan, will work on VXS backplane clock distribution. | ||
+ | * Some discussion ensued concerning what must be demonstrated for the subsystem and CD-3 reviews. | ||
+ | ** critical items not yet demonstrated. | ||
+ | * More discussion about subsystem review May 2008, scope is what has not been previously reviewed (Trigger, DAQ, etc). | ||
+ | ** CD-3 (Lehman) review will view reports of other subsystem reviews, but likely will not probe more deeply. | ||
+ | |||
+ | |||
+ | '''Chris discussed results of manpower meeting with Claus et al:''' | ||
+ | |||
+ | |||
+ | |||
+ | |||
'''Dave Doughty discussed how to include the tagger in the trigger:''' | '''Dave Doughty discussed how to include the tagger in the trigger:''' | ||
'''Elliott presented the list of online major milestones:''' | '''Elliott presented the list of online major milestones:''' |
Revision as of 16:17, 17 December 2007
Contents
Agenda
- Review of minutes from 29-Nov-2007 meeting
- Progress and milestones from JLab Electronics Group - Chris C.
- Tagger in trigger - Dave D.
- Online milestones for Subsystem review May-2008 and CD-3 review Jul-2008- Elliott
- Online Action Items
Time/Location
2:00pm Fri 14-Dec-2007 Cebaf Center F326
To connect by telephone:
1) dial:
+1-800-377-8846 : US
+1-888-276-7715 : Canada
+1-302-709-8424 : International
2) enter participant code: 39527048# (remember the "#")
Announcements
- Minor rewording in Wiki pages: DAQ/Online/Controls ==> Trigger/DAQ/Monitoring/Controls.
- Suggestion to form Hall D electronics pool.
Next Meeting
Next meeting will be in Jan, date TBD.
New Action Items from this Meeting
- Add to online milestones document (Elliott):
- more specific electronics milestones
- demonstration of full crate-sum trigger readout
- add dates for each milestone
- Give Elke items for the Hall D Action Item Tracker (Elliott)
- more detailed than major milestonen
- include names, dates, etc.
Minutes
Attendees: Elliott W, Dave A, Chris C, Fernando B, Mark I, Elton S, Dave D, Ed J, Carl T, Simon T.
Chris Cuevas gave an update on electronics:
- Many specs and drawings in draft state, prototypes are coming.
- Manpower is a big problem given deadlines, esp. for the crate-sum module.
- Two more 20-slot VXS crates on order.
- Slightly behind on FADC October milestones, no full crate tests yet.
- Hai will work on FADC after completing an Accelerator project.
- New hire will arrive in Jan, will work on VXS backplane clock distribution.
- Some discussion ensued concerning what must be demonstrated for the subsystem and CD-3 reviews.
- critical items not yet demonstrated.
- More discussion about subsystem review May 2008, scope is what has not been previously reviewed (Trigger, DAQ, etc).
- CD-3 (Lehman) review will view reports of other subsystem reviews, but likely will not probe more deeply.
Chris discussed results of manpower meeting with Claus et al:
Dave Doughty discussed how to include the tagger in the trigger:
Elliott presented the list of online major milestones: