Difference between revisions of "Photon Beam Commissioning Discussion Sep 3, 2014"
From GlueXWiki
(→Action Items) |
(→Action Items) |
||
Line 17: | Line 17: | ||
* Hovanes is preparing photomultipliers that can be used to measure beam loss along the beamline. | * Hovanes is preparing photomultipliers that can be used to measure beam loss along the beamline. | ||
* Complete the tagger layout with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton) | * Complete the tagger layout with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton) | ||
+ | * Circulate the updated version of ICD (Elton) | ||
== Agenda == | == Agenda == |
Revision as of 09:12, 21 August 2014
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
- Richard will provide a "sacrificial" board with 30 SiPMs to register neutron damage during initial electron beam tune.
- Hovanes is preparing photomultipliers that can be used to measure beam loss along the beamline.
- Complete the tagger layout with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)
- Circulate the updated version of ICD (Elton)
Agenda
- Announcements
- Comments on ARR
- Accelerator and Hall D Interface Document - update
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Other business
Minutes
Attending: