Difference between revisions of "Run Planning Meeting Notes, August 6 - 12, 2020"
From GlueXWiki
(→Friday, August 7) |
(→Friday, August 7) |
||
Line 11: | Line 11: | ||
#* [https://logbooks.jlab.org/entry/3821523 Trigger check-out] (Sasha) | #* [https://logbooks.jlab.org/entry/3821523 Trigger check-out] (Sasha) | ||
#* [https://logbooks.jlab.org/entry/3821561 TagH] and PS HV scan, interrupted by pass change | #* [https://logbooks.jlab.org/entry/3821561 TagH] and PS HV scan, interrupted by pass change | ||
− | #* No beam since | + | #* Storm, optics tuning, several issues, transformer repair |
+ | #* No beam since, expected only this afternoon | ||
# Reports/Issues | # Reports/Issues | ||
#* Remind MCC to put in dumplet when changing radiators | #* Remind MCC to put in dumplet when changing radiators |
Revision as of 08:06, 7 August 2020
<- Back to Run Coordination Meetings:Fall2019 Run
Friday, August 7
- Last 24 hours
- Diamond alignment check (Hovanes)
- Coherent edges are reproducible to about 20 MeV, tweaking may be necessary
- Add screen shots of the coherent edges to logbook
- "force para/perp" and "save as default" for each of the four settings
- Trigger check-out (Sasha)
- TagH and PS HV scan, interrupted by pass change
- Storm, optics tuning, several issues, transformer repair
- No beam since, expected only this afternoon
- Diamond alignment check (Hovanes)
- Reports/Issues
- Remind MCC to put in dumplet when changing radiators
- BCal Pulser?
- Monitoring:
- CPP Status
- Run Plan
- Harp Scan
- Complete first production cycle with 350nA
Thursday, August 6
- Last 24 hours
- 5th pass separator problems after thunderstorm in the evening
- Beam recovered around midnight
- Harp scan: results
- Radiation levels checked: similar to spring
- Reports/Issues
- TagM was set to high gain mode during night, saturates, no meaningful data [1]
- Diamond alignment: coherent edge too far off (Beni)
- Bleed through from Hall B
- Run Plan
- Diamond alignment (Hovanes)
- Trigger, PS, TagH check (Sasha)
- Pass change at noon