== Dry Run Schedule for the Review == | == Dry Run Schedule for the Review == | ||
− | + | === First round of dry runs (week of October 27) === | |
− | + | * Monday L102/104 October 27 | |
− | # Second round of dry runs (weeks of November 3 and 10) | + | #Overview of Hall D Detector E. C. Aschenauer |
− | + | #12 GeV Electron Beam Y. Roblin | |
+ | #Photon Beam Overview R. Jones | ||
+ | #Beam Simulations A. Somov | ||
+ | #Photon Beam Line T. Whitlatch | ||
+ | #Magnet Design J. Stewart | ||
+ | #Tagger Optics D. Sober | ||
+ | #Fixed Array Hodoscope F. Klein | ||
+ | #Microscope I. Senderovich | ||
+ | #Pair Spectrometer J. Stewart | ||
+ | #Diamond Selection and Testing R. Jones | ||
+ | |||
+ | === Second round of dry runs (weeks of November 3 and 10) === | ||
+ | * Wednesday F326/327 November 5 | ||
+ | #Overview of Hall D Detector E. C. Aschenauer | ||
+ | #12 GeV Electron Beam Y. Roblin | ||
+ | #Photon Beam Overview R. Jones | ||
+ | #Beam Simulations A. Somov | ||
+ | #Photon Beam Line T. Whitlatch | ||
+ | #Magnet Design J. Stewart | ||
+ | #Tagger Optics D. Sober | ||
+ | #Fixed Array Hodoscope F. Klein | ||
+ | #Microscope I. Senderovich | ||
+ | #Pair Spectrometer J. Stewart | ||
+ | #Diamond Selection and Testing R. Jones | ||
+ | === Main Review === | ||
# Review: November 19 and 20. | # Review: November 19 and 20. | ||
# issues that need special attention | # issues that need special attention |
Revision as of 18:46, 8 October 2008
Contents
The Hall D/GlueX Tagger and Beamline Review
- Agenda
- November 19-20 Review Website (halld guest)
- Previous Reviews
Material Prepared for the Review
- Pre-brief Material for the reviewers
- GlueX-doc-1063 GlueX Physics and Detector Performance Metrics
- Final Talks
- GlueX-doc-1xxx GTemplate
Relevant Wiki Pages
- Description Photon Beam
- Biweekly Meetings
- Drawings (Tim)
Dry Run Schedule for the Review
First round of dry runs (week of October 27)
- Monday L102/104 October 27
- Overview of Hall D Detector E. C. Aschenauer
- 12 GeV Electron Beam Y. Roblin
- Photon Beam Overview R. Jones
- Beam Simulations A. Somov
- Photon Beam Line T. Whitlatch
- Magnet Design J. Stewart
- Tagger Optics D. Sober
- Fixed Array Hodoscope F. Klein
- Microscope I. Senderovich
- Pair Spectrometer J. Stewart
- Diamond Selection and Testing R. Jones
Second round of dry runs (weeks of November 3 and 10)
- Wednesday F326/327 November 5
- Overview of Hall D Detector E. C. Aschenauer
- 12 GeV Electron Beam Y. Roblin
- Photon Beam Overview R. Jones
- Beam Simulations A. Somov
- Photon Beam Line T. Whitlatch
- Magnet Design J. Stewart
- Tagger Optics D. Sober
- Fixed Array Hodoscope F. Klein
- Microscope I. Senderovich
- Pair Spectrometer J. Stewart
- Diamond Selection and Testing R. Jones
Main Review
- Review: November 19 and 20.