Difference between revisions of "SRC/CT Run Plan"

From GlueXWiki
Jump to: navigation, search
(Plan for 8 Nov-6 Dec)
(Plan for 8 Nov-6 Dec)
Line 102: Line 102:
 
| <span style="color:blue"> Production with C target </span>  
 
| <span style="color:blue"> Production with C target </span>  
 
| 68  ( 17 days )  <br /> 2   
 
| 68  ( 17 days )  <br /> 2   
| 140   <br /> 50  
+
| 150   <br /> 50  
 
|  4x10<sup>-4</sup>
 
|  4x10<sup>-4</sup>
 
| <br /> Insert CCAL, HV on for low-energy TAGH
 
| <br /> Insert CCAL, HV on for low-energy TAGH

Revision as of 19:37, 2 December 2021

Plan for 8 Nov-6 Dec

Note that shifts here correspond to accelerator shifts.

See visually here

The standard configuration of the GlueX detector will be used during the SRC run

Activity Time (shifts) Beam current (nA) Radiator (R.L.) Comment
Liquid He target
Tune beam to tagger hall 3
Ion chamber calibration
Radiation monitor check
0.6
Harp scan for electron beam 0.2 Establish photon beam
Calib active collimator 0.5
Align JD70 - 105 radiator 1.5 4x10-4
Detector checkout, Trigger / DAQ tuning 3 10 - 150 same
Collect data in raw mode 0.1 10 - 150
Total 2.5 days
Production with 4He target
48 ( 12 days )
1
1
150
150
50
4x10-4
4.5x10-4 (AMO)
4x10-4


Insert CCAL, HV on for low-energy TAGH
Empty (He) target run 2
Target change to D 2.0
Production with D target 8 (2 days) 140
Insert CCAL, HV on for low-energy TAGH
TAC run (use CCAL as TAC) 2 shifts < 5 2x10-5 Empty liquid target
Target change to C
Ramp the solenoid magnet down
Install and align target
Ramp the magnet up

1.25
1.5
1.25

-
-
-

-
-
-
Production with C target 68 ( 17 days )
2
150
50
4x10-4
Insert CCAL, HV on for low-energy TAGH
Target change to D
Ramp the solenoid magnet down
Install and align target
Ramp the magnet up

1.25
1.5
1.25

-
-
-

-
-
-
Production with D target 24 (6 days) 140
Total 42 days

General Conditions

Item Polarized Beam
Beam Energy 10.9 GeV
Beam Current 140 nA
Active Collimator (Inner) optimal coordinates x = 0 mm, y = −0.2 mm (Will be updated)
BPM (IPM5C11B) optimal coordinates x = −0.5 mm, y = +1.0 mm
Tagger Quadrupole (MQPAD00) Current −4.2 A
Radiator JD70-105, 47 μm 4·10-4 R.L., 4.5·10 -4 R.L. AL radiator (30 µm Al), 2·10-5 R.L. AL
Coherent Peak Position 8.6 GeV
Beam Profiler retracted
Collimator 5.0 mm
Pair Converter Be 75 μm
Pair Spect. Magnet Current (set point) 850 A
GlueX Solenoid 1350 A
TAC retracted


Corrections to the photon flux due to the beam energy

  • Run conditions approved by PAC and ERR
    • Electron beam energy: 12 GeV
    • Energy range of interest: 8 - 9 GeV,
    • Photon flux: 2·107 phot / sec
  • Reduction of the beam energy from 12 GeV to 10.8 GeV
    • R = Nphot 12 GeV / Nphot 10.8 GeV
    • R (0 - 8 GeV) = 1.17
    • R (0 - 12 GeV) = 1.2
    • R (8 - 9 GeV) = 2
    • R (8 - 12 GeV) = 1.93

Setting up photon beam


SRC production

  • Standard configuration: Production on JD70-105 radiator. 2h runs and no more, as it may be hard to correct for calibration drifts. Cycle over 4 sets of runs: 0o, then 90o, then 45o, then 135o.


Trigger Types

List of triggers used in the SRC (page will be updated)