* Wednesday pm - cooling water outage [https://logbooks.jlab.org/entry/4089930 summary] and [https://logbooks.jlab.org/entry/4089879 more stripcharts]. We lost about 2h beam-time time fixing problems and waiting for the target to refill; it was another 2h before the BCAL chiller temps returned to normal. | * Wednesday pm - cooling water outage [https://logbooks.jlab.org/entry/4089930 summary] and [https://logbooks.jlab.org/entry/4089879 more stripcharts]. We lost about 2h beam-time time fixing problems and waiting for the target to refill; it was another 2h before the BCAL chiller temps returned to normal. | ||
− | + | * [https://logbooks.jlab.org/entry/4090024 One Ar cylinder is empty] | |
=== Shift Summaries === | === Shift Summaries === |
Revision as of 08:13, 24 November 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Our next planned meeting is on Monday Nov 28
The plan
- Continue production running at 200nA with a full target until further notice (after the weekend).
Achievements
- Production running with full target.
- Filled the target on Wednesday morning after approximately 2B triggers with empty target.
- Raw mode cosmics run 111571 (Beni)
- FCAL base changed (Malte)
- Several locked up FCAL bases reset Wed early riser Wed day
Issues
- Wednesday pm - cooling water outage summary and more stripcharts. We lost about 2h beam-time time fixing problems and waiting for the target to refill; it was another 2h before the BCAL chiller temps returned to normal.