= Minutes = | = Minutes = | ||
− | # | + | # Run preparations |
#* Beni did new baseline calibrations of the CDC. Found one channel that has some noise. | #* Beni did new baseline calibrations of the CDC. Found one channel that has some noise. | ||
+ | #* The FDC chiller that was installed earlier this week failed to regulate the temperature. It was replaced with the spare one, which means we don't have a spare at the moment. | ||
#* The target is still on the platform. Most likely tomorrow will be pushed in, then Lubomir plans to look with a scope on the four groups (of 24) channels that exhibit about half of the full fADC range. | #* The target is still on the platform. Most likely tomorrow will be pushed in, then Lubomir plans to look with a scope on the four groups (of 24) channels that exhibit about half of the full fADC range. | ||
#* We aim to take comics over the weekend. | #* We aim to take comics over the weekend. | ||
+ | #*Sergey and Lubomir will install several detectors to be tested parasitically at the left PS arm. These include small GEM-TRD, 3 calorimeter modules, and the GEM trackers. The GEM trackers are supposed to be positioned upstream of the shielding, but Eugene suggested first to test them downstream, then to installed them at their place. |
Revision as of 23:35, 5 January 2023
Thu 1/5/2023 2pm
Agenda
- Run preparations:
- CDC
- FDC
- Tracking
- GEM-TRD
- Other
Minutes
- Run preparations
- Beni did new baseline calibrations of the CDC. Found one channel that has some noise.
- The FDC chiller that was installed earlier this week failed to regulate the temperature. It was replaced with the spare one, which means we don't have a spare at the moment.
- The target is still on the platform. Most likely tomorrow will be pushed in, then Lubomir plans to look with a scope on the four groups (of 24) channels that exhibit about half of the full fADC range.
- We aim to take comics over the weekend.
- Sergey and Lubomir will install several detectors to be tested parasitically at the left PS arm. These include small GEM-TRD, 3 calorimeter modules, and the GEM trackers. The GEM trackers are supposed to be positioned upstream of the shielding, but Eugene suggested first to test them downstream, then to installed them at their place.