Difference between revisions of "JEF meeting, March 10, 2023"
From GlueXWiki
(→Agenda) |
|||
Line 31: | Line 31: | ||
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students] | ||
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ] | ||
− | |||
* '''Light Monitoring System''' -- Arshak | * '''Light Monitoring System''' -- Arshak | ||
* '''Simulations/Analysis''' | * '''Simulations/Analysis''' | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− |
Revision as of 09:08, 10 March 2023
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Preparation of parts for FCAL2 modules -- Sasha
- Available crystals:
- 1450 (modules)
- 32 (ready for fabrication)
- 40 (installed on CCAL) available on March 20
- (some CCAL crystals from the inner part will not be used for the FCAL2)
- 95 expect to receive from CRYTUR in May [1]
- Total 1617
- Wrapped crystals: 32 (Mindy)
- George (DSG group) finished with disassembling CCAL modules and removing LMS caps. Will work on preshaping ESR reflectors for CRYTUR. The oven will be ready in a week.
- Mindy (DSG group) solder wires to sockets (while waiting for crystals). More crystals will come from the CCAL after the run in the end of March.
- Parts. 60 remaining PMT housings and cylinders have been ordered by Tim; should be ready for fabrication in about 2 months
- Available crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1455 (5 modules fabricated since last week)
- Currently available for fabrication: 27
- Fabricated modules: Total 1455 (5 modules fabricated since last week)
- Testing of PMT dividers -- Sasha / Arshak
- FCAL2 modules with dividers installed on the CCAL [2]
- Installation of the FCAL2 detector -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light Monitoring System -- Arshak
- Simulations/Analysis