Difference between revisions of "ECAL Commissioning"
From GlueXWiki
(Created page with "Commissioning run plan") |
|||
Line 1: | Line 1: | ||
+ | * DAQ configuration | ||
+ | |||
+ | * Tests with the LMS | ||
+ | |||
+ | * Cosmic tests | ||
+ | :: initial gain calibration | ||
+ | |||
+ | * HV settings | ||
+ | |||
[[Commissioning run plan]] | [[Commissioning run plan]] |
Revision as of 09:03, 6 September 2024
- DAQ configuration
- Tests with the LMS
- Cosmic tests
- initial gain calibration
- HV settings