Difference between revisions of "Solenoid Coil Test in Test Lab"
From GlueXWiki
m |
m |
||
Line 57: | Line 57: | ||
* Platform | * Platform | ||
+ | ** Entire platform and supports will be moved when changing coils. | ||
+ | ** Must account for magnetic forces. | ||
+ | ** Ladder needs to be shortened and straightened. | ||
+ | ** Must include cable trays and strain relief, especially for power connections. | ||
+ | ** | ||
+ | |||
* Rails | * Rails | ||
+ | ** Currently in transportainer at IU, George will have a look when he goes out there. | ||
+ | |||
* Cryo can and heat exchanger | * Cryo can and heat exchanger | ||
+ | ** RFQ out for cryo can, no delivery date yet. | ||
+ | |||
* Piping | * Piping | ||
+ | ** Not clear where N2 vent this will be routed. | ||
+ | ** Must incorporate drip pan under N2 vent due to icing. | ||
+ | |||
* Electrical power | * Electrical power | ||
+ | ** Need to work out where outlets are needed. | ||
+ | |||
+ | |||
* Power supply | * Power supply | ||
+ | ** Integral dump resistor. | ||
+ | ** Need switch nearby. | ||
+ | |||
+ | |||
* Coils and yokes | * Coils and yokes | ||
+ | ** Are yoke modifications are needed? | ||
+ | |||
+ | |||
* Controls system | * Controls system | ||
− | * Misc | + | ** Will wire up as per final system. |
+ | ** Should we go with separate chassis for each coil? | ||
+ | |||
+ | |||
+ | * Misc tools, tables, chairs, ladders, etc. | ||
+ | ** What do we need? Can we beg, borrow, and/or steal? | ||
+ | |||
* '''To Do:''' | * '''To Do:''' | ||
Line 74: | Line 103: | ||
** Order remaining piping - ? | ** Order remaining piping - ? | ||
** Design cryo and electrical/electronics break system - George and Mark S | ** Design cryo and electrical/electronics break system - George and Mark S | ||
+ | ** Arrange for yoke modifications if needed - George | ||
+ | ** Determine if sensible to use one PLC chassis per coil - Mark S and Elliott | ||
+ | ** Order signal conditioners and related items - Mark S and Elliott | ||
+ | ** Order PLC components - Elliott | ||
Revision as of 10:03, 19 June 2009
Notes and to-do lists for the solenoid coil tests this summer and fall.
Contents
Test Area
- Notes:
- Area in the test lab is 20'6" x 25'9", currently filled with coils and coil parts.
- Bob Bennett is Test Lab "space czar."
- Wayne is designing overall layout.
- May be able to get space in adjacent areas (QWeak construction and SRF cavity storage areas).
- May need extra space for large power supply (6' x 5', 5' H, 5000 lbs) and switch, and to avoid placing controls racks in large B field.
- Must maintain clear areas around racks and power supply, and cannot block pedestrian walkways.
- Platform is 172" x 160", cryo can will sit on top.
- Platform must be removed to swap coils, and all connections to it must be broken.
- Area has two 25T cranes, but need both (and spreader bar) to lift heaviest yoke (45 tons).
- Need come-alongs and anchors to move yokes and coils along rails.
- Some areas will need to be roped off due to high B fields (> 5 Gauss, for pacemakers)
- May need to remove some fences.
- To Do:
- Look into getting space in adjacent areas - George
- Look into possibility of locating computer in control room (contact Joe Preble, Mark Drury)- Elliott
- Distribute Floyd's B field map for single coil, no cladding - George
- Determine location of all components - Wayne
- Investigate sensitivity of electronic equipment to B fields - Elliott
- Find spreader bar - George
- Determine areas to be roped off due to high B field - Floyd, George
- Enable building access for everyone.
Infrastructure
- Notes:
- Platform borrowed from Hall A.
- Rails currently at IU.
- Have or can borrow all material moving equipment, or will contract out to rigging firm.
- Have or can borrow all tools needed.
- Controls racks coming from Randy H or from computer center.
- Need 60 W liquid He, Test Lab supply capable of 500 W, but share with Cryo group.
- Must account for magnetic forces on all structures, perhaps as much as 20-30 Gauss static B field.
- To Do:
- Produce overall system diagram - George
- Design structures and mechanical components, route cables and piping, etc. - Wayne
- Arrange for piping designer - George
- Design piping to vent N2.
- Design warm and cold He supply/return systems, LN2 supply system.
- Retrieve rails from IU - George and Elliott
- Get three racks from Randy H or from CC - Mark S and Elliott W
- Determine cryogen supply/return needs - George
- Arrange for cryogen supply/return with Dana Arenius (and Kelly Dixon?)- George and Elliott
Components
- Platform
- Entire platform and supports will be moved when changing coils.
- Must account for magnetic forces.
- Ladder needs to be shortened and straightened.
- Must include cable trays and strain relief, especially for power connections.
- Rails
- Currently in transportainer at IU, George will have a look when he goes out there.
- Cryo can and heat exchanger
- RFQ out for cryo can, no delivery date yet.
- Piping
- Not clear where N2 vent this will be routed.
- Must incorporate drip pan under N2 vent due to icing.
- Electrical power
- Need to work out where outlets are needed.
- Power supply
- Integral dump resistor.
- Need switch nearby.
- Coils and yokes
- Are yoke modifications are needed?
- Controls system
- Will wire up as per final system.
- Should we go with separate chassis for each coil?
- Misc tools, tables, chairs, ladders, etc.
- What do we need? Can we beg, borrow, and/or steal?
- To Do:
- Understand how to deal with dump resistor in power supply - Mark S
- Order cryo can - George
- Verify all cryo transfer lines and U-tubes are available on site - Mark S and George
- Verify we can borrow heat exchanger from Hall A - George
- Get heat exchanger - Mark S
- Order remaining piping - ?
- Design cryo and electrical/electronics break system - George and Mark S
- Arrange for yoke modifications if needed - George
- Determine if sensible to use one PLC chassis per coil - Mark S and Elliott
- Order signal conditioners and related items - Mark S and Elliott
- Order PLC components - Elliott
Programming
- Notes:
- Mark W will do all programming.
- Can borrow lots of code from Steve Lassiter and co.
- Single computer will perform all control and monitoring tasks.
- To Do:
- Install new memory in controls computer - Elliott and Mark W
- Purchase new software licenses - Elliott
- Install all software on controls computer - Mark W
- Borrow code from Steve Lassiter - Mark W
- Explain overall control strategy to Mark W - George
- Determine what needs to be archived and how often - George
- Design and implement full control and archiving system - Mark W
Staging
- Notes:
- Will instrument controls racks in F117, then move to Test Lab.
- Will instrument for final 4-coil system.
- To Do:
- Rearrange F117 - Mark S and Beni
- Get and move 3 racks into F117 - Mark S
- Verify adequate staging areas available in Test Lab - George, Wayne and Mark S
Reviews
- Notes:
- Micro-review of PLC vendor choice completed, waiting for report.
- Need cryo, electrical, mechanical, and operations reviews.
- To Do:
- Write thank-you letter to Jonathan Creel and Omar Garza for participating in PLC vendor review - Elliott
- Write appropriate documentation - George, Mark S, Wayne and Elliott
- Set up all reviews - George and Elliott
Construction
- Notes:
- Do we have enough manpower?
- To Do:
- Arrange for any coil or yoke modifications - George
- Order controls equipment - Mark S and Elliott
- Arrange for telephone and networking in test area - Elliott
- Arrange for installation of electrical infrastructure - Mark S
- Move controls racks to Test Lab - Mark S
- Move computer to Test Lab - Mark W and Elliott
- Install all components - Mark S
- Hook up controls system - Mark S, Mark W and Elliott
- Verify operation of control/archiving system - Mark W, Mark S, George and Elliott
Coil Tests
- Notes:
- Purpose:
- Verify correct operation of all coils.
- Measure coil strains up to full current (1600 A).
- Will take about one month per coil.
- Will take a few days to cool down a single coil (warm up?).
- Purpose:
- To Do:
- Create test plan - George