'''Agenda''' | '''Agenda''' | ||
− | * FastTrack schedule: status of merging | + | * FastTrack schedule: status of merging two versions - George, Chuck |
* Any news on using QWeak area? - Tom | * Any news on using QWeak area? - Tom | ||
* Are modifications to power supply dump resistor wiring needed? - Mark S | * Are modifications to power supply dump resistor wiring needed? - Mark S | ||
Line 29: | Line 29: | ||
* Safety reviews - George, Elliott | * Safety reviews - George, Elliott | ||
* 5 G contours - George | * 5 G contours - George | ||
− | * Chris' group can do CAD rack layout - Elliott | + | * Chris' group can do CAD rack layout if we wish - Elliott |
Revision as of 11:30, 1 December 2009
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 3-Dec-2009 9:45 am ARC 428
Agenda
- FastTrack schedule: status of merging two versions - George, Chuck
- Any news on using QWeak area? - Tom
- Are modifications to power supply dump resistor wiring needed? - Mark S
- Status of interface to cryo can - George
- Status of pressure relief system design - George
- Ordering cryo can - George
- Ordering platform - George
- Construction/installation sequence drawings - George, Chuck
- Ordering remaining controls instrumentation and components - Scot, Elliott
- P&I, controls drawings, narrative - George, Mark S, Mark W
- Bigger door in F117 - Tom
- Begin wiring effort in F117 - Scot
- PLC programming and testing - Mark W
- Coil 1 testing and wire replacement - George
- Coil 2 cost/schedule review, etc. - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails from IUCF - Tom
- Safety reviews - George, Elliott
- 5 G contours - George
- Chris' group can do CAD rack layout if we wish - Elliott