* Latest coil test schedule - Tom | * Latest coil test schedule - Tom | ||
* Any news on using QWeak area? - Tom | * Any news on using QWeak area? - Tom | ||
− | * Are modifications to power supply dump resistor wiring needed? - Mark S | + | * Status of getting bigger door in F117 - Tom |
− | * | + | * Are modifications to the power supply dump resistor wiring needed? - Mark S |
+ | * Do we need a redundant PLC system - Elliott | ||
* Status of interface to cryo can - George | * Status of interface to cryo can - George | ||
* Status of pressure relief system design - George | * Status of pressure relief system design - George | ||
Line 21: | Line 22: | ||
* Ordering remaining controls instrumentation and components - Scot, Elliott | * Ordering remaining controls instrumentation and components - Scot, Elliott | ||
* P&I, controls drawings, narrative - George, Mark S, Mark W | * P&I, controls drawings, narrative - George, Mark S, Mark W | ||
− | |||
* Begin wiring effort in F117 - Scot | * Begin wiring effort in F117 - Scot | ||
* PLC programming and testing - Mark W | * PLC programming and testing - Mark W |
Revision as of 12:39, 2 December 2009
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 3-Dec-2009 9:45 am ARC 428
Agenda
- FastTrack schedule: status of merging two versions - George, Chuck
- Latest coil test schedule - Tom
- Any news on using QWeak area? - Tom
- Status of getting bigger door in F117 - Tom
- Are modifications to the power supply dump resistor wiring needed? - Mark S
- Do we need a redundant PLC system - Elliott
- Status of interface to cryo can - George
- Status of pressure relief system design - George
- Status of ordering cryo can - George
- Ordering platform - George
- Construction/installation sequence drawings - George, Chuck
- Ordering remaining controls instrumentation and components - Scot, Elliott
- P&I, controls drawings, narrative - George, Mark S, Mark W
- Begin wiring effort in F117 - Scot
- PLC programming and testing - Mark W
- Coil 1 testing and wire replacement - George
- Coil 2 cost/schedule review, etc. - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Tom
- Safety reviews - George, Elliott
- 5 G contours - George
- Chris' group can do CAD rack layout if we wish - Elliott