Difference between revisions of "Coil Test Weekly Meeting 11-Mar-2010"
From GlueXWiki
m |
m |
||
Line 10: | Line 10: | ||
* Networking, computers and accounts for coil test - Elliott | * Networking, computers and accounts for coil test - Elliott | ||
− | * Safety review, ODH, etc. - Elliott, Josh | + | * Safety review meeting, ODH analysis,TOSP, etc. - Elliott, Josh |
− | * P&I | + | * P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S |
* Status of PLC programming - Mark W | * Status of PLC programming - Mark W | ||
* A-B software licenses, HMI and web programming - Elliott, Yi | * A-B software licenses, HMI and web programming - Elliott, Yi | ||
− | * What PLC display pages are needed - Josh | + | * What PLC display pages are needed (HMI and web) - Josh |
* Wiring progress in F117 - Scot | * Wiring progress in F117 - Scot | ||
+ | * How will we test PLC program - Mark W, Scot, Mark S | ||
* Installation in current and QWeak areas - Tom | * Installation in current and QWeak areas - Tom | ||
− | * | + | * Tying into existing vent piping system - Tom |
* Status of miscellaneous parts orders - George | * Status of miscellaneous parts orders - George | ||
− | * Coil 1 status - George | + | * Coil 1 repair status - George |
− | * Coil 2 | + | * Coil 2 repair status - George |
− | * Coil 3 | + | * Coil 3 progress at IUCF - George |
* Coil 4 controls wiring replacement - George | * Coil 4 controls wiring replacement - George | ||
* 5 G contours - George | * 5 G contours - George | ||
* Coil Test [[Solenoid_Coil_Test | Top To-Do items]] | * Coil Test [[Solenoid_Coil_Test | Top To-Do items]] |
Revision as of 10:52, 9 March 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 11-Mar-2010 9:45am ARC 428
Agenda
- Networking, computers and accounts for coil test - Elliott
- Safety review meeting, ODH analysis,TOSP, etc. - Elliott, Josh
- P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
- Status of PLC programming - Mark W
- A-B software licenses, HMI and web programming - Elliott, Yi
- What PLC display pages are needed (HMI and web) - Josh
- Wiring progress in F117 - Scot
- How will we test PLC program - Mark W, Scot, Mark S
- Installation in current and QWeak areas - Tom
- Tying into existing vent piping system - Tom
- Status of miscellaneous parts orders - George
- Coil 1 repair status - George
- Coil 2 repair status - George
- Coil 3 progress at IUCF - George
- Coil 4 controls wiring replacement - George
- 5 G contours - George
- Coil Test Top To-Do items