Difference between revisions of "July 29, 2010 Readout"
From GlueXWiki
m (July 30, 2010 Readout moved to July 29, 2010 Readout: incorrect date) |
(→Tentative Agenda) |
||
Line 22: | Line 22: | ||
# Announcements | # Announcements | ||
# Review of Action Items | # Review of Action Items | ||
+ | # Bcal thresholds and resolution at low energies (Matt) | ||
+ | # [[SiPM Radiation Hardness Test]] (Update from Yi) | ||
+ | # Geometry | ||
# Update - USM | # Update - USM | ||
#* Status of statement of work (SOW) | #* Status of statement of work (SOW) | ||
# Simulation runs | # Simulation runs | ||
# Cosmic-ray setup at UofR | # Cosmic-ray setup at UofR | ||
− | |||
− | |||
# Light guides | # Light guides | ||
#* [https://mailman.jlab.org/pipermail/halld-cal/2010-July/000208.html Zisis Discussions with Stefano Miscetti] | #* [https://mailman.jlab.org/pipermail/halld-cal/2010-July/000208.html Zisis Discussions with Stefano Miscetti] |
Revision as of 08:36, 29 July 2010
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone in CC L207 is 757-269-7084
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone connection only upon request.
Contents
Items for followup from previous meeting
- Testing goals and setup (Serguei) - addressed in agenda below
- Will to find out if there is any feedback from USM on terms and conditions from our procurement package.
- Will to update statement of work for USM contract and develop detailed schedule.
- Collect this information of testing on the wiki for ease of presenting information. (USM)
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Bcal thresholds and resolution at low energies (Matt)
- SiPM Radiation Hardness Test (Update from Yi)
- Geometry
- Update - USM
- Status of statement of work (SOW)
- Simulation runs
- Cosmic-ray setup at UofR
- Light guides
Minutes
Attendees: