Difference between revisions of "GlueX TOF Meeting, March 14, 2013"
From GlueXWiki
(→Minutes) |
(→Construction Status) |
||
Line 32: | Line 32: | ||
* '''JLab''': Chuck Hutton, Mark Ito (chair), Beni Zihlmann | * '''JLab''': Chuck Hutton, Mark Ito (chair), Beni Zihlmann | ||
− | =Construction Status= | + | ==Construction Status== |
Paul led us through several photographs of construction progress at FSU (username: gluex, password: the-standard-gluex-password). | Paul led us through several photographs of construction progress at FSU (username: gluex, password: the-standard-gluex-password). | ||
Line 43: | Line 43: | ||
** Fabricated Components as they arrived | ** Fabricated Components as they arrived | ||
* [http://hadron.physics.fsu.edu/wiki/index.php/Attaching_PMTs_to_module Attaching PMTs to module]: clamp arrangement for gluing PMTs to light guides | * [http://hadron.physics.fsu.edu/wiki/index.php/Attaching_PMTs_to_module Attaching PMTs to module]: clamp arrangement for gluing PMTs to light guides | ||
+ | |||
+ | ==Readiness Review== | ||
+ | |||
+ | The review is scheduled for Friday, March 22 at FSU. | ||
+ | |||
+ | ===Agenda=== | ||
+ | |||
+ | We went over the [http://hadron.physics.fsu.edu/wiki/index.php/Readiness_Review agenda] that Paul had prepared. There is a full schedule of touring facilities in the morning. We agreed on two changes: | ||
+ | # Allow more time, at least and hour, for a presentation of construction status in the morning. This will push the Overview of Technical Procedures session to after lunch. | ||
+ | # Block some time for financial types from JLab and FSU to discuss invoicing and other related matters. |
Revision as of 13:40, 14 March 2013
GlueX TOF Meeting
Thursday, March 14, 2013
10:00 am EDT
JLab: CEBAF Center, F326/327
Contents
Agenda
- Announcements
- Review of last TOF bi-weekly meeting
- Construction status
- first article modules
- MiniTOF
- status of components
- Readiness Review, March 22
Communication
Videoconference
- ESNet: 8542553
- SeeVogh: SeeVogh site
Slides
Talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2013-1Q
on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2013-1Q/ .
Minutes
Present:
- FSU: Maurizio Bertoli, Paul Eugenio, Sasha Ostrovidov
- JLab: Chuck Hutton, Mark Ito (chair), Beni Zihlmann
Construction Status
Paul led us through several photographs of construction progress at FSU (username: gluex, password: the-standard-gluex-password).
- First Article Modules: standard, half-width, and half length on the construction table, wrapped and with light guides and PMTs attached.
- MiniTOF:
- MiniTOF Support Stand
- Assembly steps
- Design drawings from Chuck
- Fabricated Components as they arrived
- Attaching PMTs to module: clamp arrangement for gluing PMTs to light guides
Readiness Review
The review is scheduled for Friday, March 22 at FSU.
Agenda
We went over the agenda that Paul had prepared. There is a full schedule of touring facilities in the morning. We agreed on two changes:
- Allow more time, at least and hour, for a presentation of construction status in the morning. This will push the Overview of Technical Procedures session to after lunch.
- Block some time for financial types from JLab and FSU to discuss invoicing and other related matters.