* Preparing for moving into the hall
 
* Preparing for moving into the hall
 
** permanent VME-based fast DAQ
 
** permanent VME-based fast DAQ
* [http://halldweb1.jlab.org/mantisbt Mantis Task Tracker]
+
* [http://halldweb.jlab.org/mantisbt Mantis Task Tracker]
 
** role in Hall D Online/Controls effort
 
** role in Hall D Online/Controls effort

Latest revision as of 10:26, 31 March 2015

Solenoid Coil Test Weekly Meeting

Location and Time

  • Fri 10-Jun-2011 9:30 am ARC 231


Agenda

  • Close out P6 solenoid equipment task
    • is everything ordered? additional PLC/Dataforth modules? PLC sequencing module?
  • Lessons learned from Coil 3
    • do we need to add or change anything?
  • Coil 2 status
    • installation status
    • hi-pot results
    • cooldown timeline
    • subcoil inductances and quench detector
      • Floyd's spreadsheet for modified taps lists inductance for 2 a,b,c,d: 1.08501, 0.6312, 0.66625, 0.92144 H
      • in pairs you get 1.71 and 1.59, ratio about 1.08
      • probably can get away with a single QD channel
    • Danfysik fault sequencer and slow dump
    • additional PLC and HMI programming
      • network loss problem?
      • auto elog entries failed
    • fast DAQ
    • replace smaller UPS
    • anything else?
  • Documentation
    • trip chains
    • anything else?
  • Will there be any auxiliary tests?
  • To-do list for the next coil
    • measure UPS lifetime under operating conditions
  • IRMIS at JLab
    • filled with BNL "training" data
  • Preparing for moving into the hall
    • permanent VME-based fast DAQ
  • Mantis Task Tracker
    • role in Hall D Online/Controls effort