CPP and NPP Run Conditions
From GlueXWiki
Activity | Duration (PAC Days) | Current | Target | Collimator | Radiator | Comment |
---|---|---|---|---|---|---|
Full target (Production) | 20 | 27 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 / JD70-107 | |
Empty Target | 1.5? | 27 nA | - | 3.4 mm | JD70-103 / JD70-107 | Run at higher current? |
Diamond Alignment | 0.5? | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 / JD70-107 | |
Trigger Commissioning | 1? | 100 nA? | Pb (0.3 mm) | 3.4 mm | JD70-103 / JD70-107 | |
Beam Energy Calibration | 0.5? | 100 nA | Pb (0.3 mm) | 3.4 mm | JD70-103 / JD70-107 | Collimator Blocking for 5 min, periodically |
TAC Runs | 1.5? | 27 | Pb (0.3 mm) | 3.4 mm | JD70-103 / JD70-107 |