Run Planning Meeting Notes, Feb 20-Feb 26, 2020
From GlueXWiki
Thursday, February 20
- Last 24 hours
- Smooth production running (18hrs/24hrs with beam)
- Reports
- Run Plan
- Production running
- Accelerator division all-hands safety meeting next Wednesday 9am-Noon. No beam.
Friday, February 21
- Last 24 hours
- Production running for us
- ESR issue which caused ~12 hour downtime for halls A-C
- MCC adjusted AD00 due to BLM trips without informing us
- Production running for us
- Reports
- [1], [2], [3] BCAL gains and temperature have changed after the incident - Mark
- Convergence looks fine
- PS enhancement after beam spot move-Justin
- Rates- Alexandre
- DIRC Tile Temperature alarm
- Run Plan
- Production running over the weekend
- List for opportunistic access? Nothing scheduled now.
- Tuesday there will be 3 hour access due to laser work
- Accelerator division all-hands safety meeting next Wednesday 9am-Noon. No beam.
- Production running over the weekend
Monday, February 24
- Last 48 hours
- Production running
- 6hr accelerator downtime Saturday afternoon due to an IOC problem that led to a series of issues [4]
- New BCAL pedestals
- MCC increased ion chamber trip level by 3-5%
- Production running
- Reports/Issues
- BCAL gains changed in a number of modules- Mark
- Convergence look normal
- Missing RCDB variables-Alex
- [5], [6] Timing calibrations not updating, should be fixed in a day or so