July 15, 2022 Tech group meeting
From GlueXWiki
Meeting Time and Place =
Friday July 15, 2022 10:30am TEDF 2504 and Teams
Agenda
- Safety - chop saw? 480 vs 208 plug
- Last day to submit PR for FY 22, Aug 19
- CPP removal/Primex install gant chart O:\halld_engineering\Installation Schedules\MS Projects
- Most likely delayed until Aug 17
- Hall D current Tasks
- FCAL Insert Module fabrication
- 120 brass straps per week needed now?
- matching mu metal to steel shields
- cutting tool
- Tent move to EEL 108
- Tagger NMR issues
- FCAL Insert Module fabrication
- FCAL Insert Drawings - 98% complete
- need cooling pipe to chiller assy
- need dark room mod for electronic patch panels, need to complete 0200 final assy dwg
- need installation drawing
- Procurement plan developed and started J:\Hall D\FCAL insert
- New Profiler install - not until August 17 - new plates arrived, need to add this to schedule
- Controls
- FDC chiller cooling water flow -
- DIRC Bar Box DP sensor
- General Maintenance
- On Call -
- ePAS Training and trial https://www.jlab.org/esh/epas