Construction schedule milestones
From GlueXWiki
Active Collimator
- 01/05/2012 - 07/10/2012 - Procument Active Collimator Components
- 07/11/2012 - 01/23/2013 - Assemble Active Collimator
- 07/11/2012 - 12/14/2012 - Program and Test Collimator Table
- 01/23/2013 - 04/24/2013 - Test Active Collimator
Tagger Microscope
- 12/02/2011 - 06/14/2012 - Procument SiPMs for Microscope
Fixed Array Hodoscope
- 01/05/2012 - 07/10/2012 - Procument Scintillator/Light Guide for Fixed Array
- 01/05/2012 - 07/10/2012 - Procument PMTs for Fixed Array
- 01/05/2012 - 07/10/2012 - Procument Dividers for Fixed Array
- 03/08/2012 - 06/08/2012 - Fabricate and Test Fixed Array Counter