Action Items from previous meetings
- Determine if swapped bias pins was accidental or in design (Chris)
- Develop front and back views of jumper sheets. Also get latest version of drawings (Jack)
- Check into AC units based on Peltier coolers for SiPM production tests (Fernando)
- Order and assemble a third SiPM puller as a backup for JLab (Jim and Scot)
- Design tooling/procedure for making the patterns for wrapping from tedlar (Jim)
- Review Fcal LED and controller monitoring boards (Fernando)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- Beam test experience (Elton)
- Connections to RTD
- Installation and space for monitoring control board
- SiPM production testing (everyone)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Chris)
- Light guide gluing setup
- Light guides
- Bcal LED boards and cabling / control boards
- Wrapping for light guides
Minutes
Attending: