JEF meeting, June 23, 2023
From GlueXWiki
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
- Preparation of parts for ECAL modules -- Sasha
- Crystals:
- - Received all crystals from CRYTUR [1].
- - Available for wrapping: 15 CRYTUR
- - Planned inspection of SICCAS crystals
- Received 1100 long signal cables
- Procurement parts for the LMS:
- - 16,400 ft of optical fibers delivered to the lab. 7,600 will be delivered in September.
- - Received all plastic caps
- - Cutting Tedlar foils, preparing silicon cookies, etc.
- Will send all electronics components to the company to fabricate dividers on Monday next week
- Crystals:
- Module fabrication -- Sasha
- Fabricated modules: Total 1586 (remaining 24 + spares)
- Report from students
- Ongoing projects -- Sasha, all
- Visual inspections of fabricated modules [2]
- -1357 modules have been checked (572 SICCAS + 785 CRYTUR) [3]
- Testing and labeling signal cables (connect flash ADC with the detector distribution panel) [4]
- - 725 long signal cables have been tested [5]
- - Cable tester and label maker
- - 12 bundles of signal cables are ready (out of 100)
- Removing signal cables from the FCAL and rearranging signal cables in the hall [6]
- Visual inspections of fabricated modules [2]
- Testing of PMT dividers -- Sasha / Vlad
- All dividers have been ordered (by Chris S.)
- Preparing setups for testing modules and dividers
- Proceedures
- Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
- Detector installation page
- Updates from the meetings with Tim's group [7]
- Discussion of the FCAL2 installation procedures [8]
- Final mapping of low-voltage cables
- Manpower and division of tasks
- Projects for summer students
- Summer Students (2023)
- Light monitoring system -- Arshak
- Simulations/Analysis