For the third coil
From GlueXWiki
To-do list
- Wiring
- rewire for coil 3 subcoils
- switch to 20 kOhm protection resistors for coil taps if needed for quench detector
- eliminiate pickup on downstream lead/splice and other channels (esp. during dump)
- understand induced voltages on taps during testing
- understand noise, signal clipping and interaction between modules
- Danfysik power supply
- fix broken transistor
- commission fault sequencer
- fix slow dump
- understand ramp-down mechanism
- understand varying fast dump time constant
- choose ground fault detection mechanism
- Danfysik quench detector
- implement divider circuit upstream of QD to eliminate effects of coil imbalances
- Instrumentation
- ensure all devices on clean power
- check out Newport controllers, flow switch, replace if needed
- implement system to isolate fault detectors and determine time sequence of trips
- understand spikes on shunt Newport
- understand effect of B field on all sensors, move devices if needed
- monitor circuit breakers?
- NI USB device
- rework Zener/divider box, needs to be fully bipolar
- eliminate noise
- A-B HMI improvements
- upgrade to 100 screen license
- implement fault sequence screens
- A-B PLC program improvements
- use custom ("add-on") instructions to simplify code
- EPICS
- EWEB screens
- update for latest tags and drawings
For the hall
- note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
- should we install a UPS on the Danfysik contactor and control boards?
- do we need additional valves, check valves, bypasses, whatever?
- do we need Dataforth voltage attenuators on coil tap channels?
- do we need active isolation of coil tap channels, etc?
- should we monitor all circuit breakers?
- should we monitor all relays?
- what is the effect of B field on sensors/relays? should some instrumentation be relocated?