Action Items from previous meetings
- Develop front and back views of jumper sheets.
Also get latest version of drawings(Jack) - Check into AC units based on Peltier coolers for SiPM production tests (Fernando)
-
Design tooling/procedure for making the patterns for wrapping from tedlar (Jim) - Review Fcal LED and controller monitoring boards (Fernando)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- Beam test experience (Elton)
- SiPM production testing (everyone)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Chris)
- Light guide gluing setup
- Wrapping for light guides
Minutes
Attending: