Action Items from previous meetings
- Check that we have all RTDs already, otherwise order (Chris)
- Jim to send BOM for mechanical parts to Chris. Chris to decide on type and size of bins needed to hold sorted parts.
- Confirm with Fernando that the labeling of boards U1-U48 and D1-D48 is ok (Elton)
- Make decisions on how to treat sensors with high dark rate (Elton)
Tentative Agenda
- Announcements
- Action Items
- Schedule for production and testing (all)
- mini-Bcal (Elton)
- SiPM production testing (Yi)
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Fernando and Chris)
- Light guide gluing setup (Scot)
Minutes
Attending: