Run Planning Meeting Notes, Nov 29-Dec 4, 2018

From GlueXWiki
Revision as of 00:45, 3 December 2018 by Billlee (Talk | contribs) (Friday, Nov 30 at 8:45)

Jump to: navigation, search

Friday, Nov 30 at 8:45

  1. Comp Cal installation
    • Completed at 6pm yesterday
  2. First sight of beam (by Comp Cal): https://logbooks.jlab.org/entry/3633247
  3. Swing and Overnight Running
    • 15 nA on Al V-wire (full running condition).
    • Lost beam around 2am (due to radiation damaged valve position sensor).
  4. FCAL is down:
  5. Run Plan:
  6. Cryo


Monday, Dec 3 at 8:45

  1. Comp Cal Status
  2. Target
    • Be target installation (tentative date is Thursday)
    • LH2 Cooling
  3. Other idea of using the low current beam
    • Coherent peak near the hodoscope low boundary test