Run Planning Meeting Notes, Dec 5-Dec 11, 2019
From GlueXWiki
<- Back to Run Coordination Meetings:Fall2019 Run
Thursday, Dec 5 at 08:45
- Last 24h:
- Straight tracks during the day, Justin & Sean working to debug recon and analyze the data
- Sean got the general detector checkout done.
- Richard's uscope scans half done, interrupted by fake PSS button press from tagger hall
- Sasha setting up trigger config for straight tracks w GEM
- MCC to start setting up hall A for RF stress testing tomorrow so trips expected during swing and owl
- Issues
- Solenoid alarm
- PSS fault
- Plan for today
- Hope to collect enough straight tracks in GEM position 1 to move to 2 when Justin gives the okay, possibly at 6am
- Move GEM to position 2, then take more data until ~4pm?
- Move GEM to position 3, then take more data until ~6am Friday?
- Plan for later
- Notes from this meeting.