May 20,2020 Tech group meeting
From GlueXWiki
Meeting Time and Place
Monday May 20, 2020 at 9am Bluejeans https://bluejeans.com/835373169
Agenda
- Covid-19 https://www.vdh.virginia.gov/coronavirus/
- Jlab Update - Media:Physics update 20may.pdf
- May go to MEDCON5 as early as May 26 to as late as June 1 (If approved by DOE)
- ON-Line training course COVID-19 Hazard Controls, should be ready this week. All HAVE to take that training before coming back on site.
- ESH to put signage on doors and other areas for occupancy, social distancing reminders, etc.
- Lab to issue a self-certification process and cards (likely, the first time you get told what the process is, and then pick up the card at the first access)
- Read and Sign the OSP for covid19 risk and exposure reduction by EH&S - it is nearly there,
- Each Division to supply a MEDCON5 list for access - Phased in half the first week, half the 2nd week
- disinfectants and cleaning supplies for general areas (like for us the Counting Houses) will be placed in areas and be available in stock room
- There will be additional guidance in OSP before work will be started
- People over 65 or have underlying medical conditions can get accommodations to work from home during MEDCON5.
- Some important points to consider are:
- We will only come back in phases. All work must be reviewed and approved by the Work Coordinator.
- Essential work is preparation for CEBAF/experiment operations, needed planning work for the scheduled accelerator down, whatever we get judged on by DOE/SC and work related to quality assurance of procurements, etc. No default work operations
- About 200 JLAB employees will be allowed back on site during MEDCON5 phased in over 2 weeks
- Request for deviation of DOE PHE charge rules has been submitted. This will affect return planning and work from home
- Communal coffee makers may be taken out of service
- Employee supplied cloth face masks required during MEDCON5 in any area where multiple people are
- Social distancing (6 ft min) required on all work unless AD approved and proper PPE
Action Items
- 1) Update list of essential personnel (Week 1' Mark, Scot, Josh, Week 2 Keith, Bobby, Chris) - Complete - Tim
- 2) Develop personnel phase in plan (2-3 groups over 2 weeks, consider loss of PHE)- in-work - Mark/Scot
- 3) Define Telework Staff - Complete (Tim, Stephanie)
- 4) Update Resumption plan with
- details on how many people to do task and how to keep 6' distancing
- Maximum occupancy in each area (including counting house and counting room) based on 170 sq ft per person.
- and review all procedures - in work - Mark/Scot
Ongoing Activities
- On Call Activity -- BCAL Chiller invalid alarm
- Updates
- Mark -- Return planning Media:D000001804P002_Beam Resumption plan_v2.pdf, Log entries, Daily Virtual walktrough https://physdiv.jlab.org/2020MedConOps/, training
- Scot -- Resumption Schedule Media:Resumption schedule_19may.pdf
- Josh -- Review Resumption Documentation training tagger window replacement
- Stephanie -- CPP Redesign for alignment, CAD
- Keith -- Vacuum training, DIRC strongback procedure, replacement water filters and UV lamps
- Bobby -- DIRC Dark Box and Mirror Box Install CAD, 3D printing, P&ID
- Chris -- Welding, Training
- Nick -- power supply temp/Flow readings
- Help desk still live -- 269-7155
- Service now for issues - https://jlab.servicenowservices.com/nav_to.do?uri=%2Fhome.do%3F
- Daily work
- Send a daily check in email response to the group
- Complete any training that is due within the next 4 months
- Do any online training that may be available
- Update documentation you are responsible for and are able to do from home
- Familiarize with Bluejeans and attend meetings as required
- Check Web EDM (CSS) screens periodically (daily)
- Check HDLOG daily and respond as needed.
- All must be available during working hours
- If you are going out of town, notify supervisor and charge vacation
- If you are sick, charge sick time
- Charge HDOPS for the actual time spent on above activities
- Charge Public Health Emergency for the remainder of hours up to 8 per day and 40 per week max.
- Fill out timesheets daily
- Anything else?