Difference between revisions of "April 23, 2024 KLONG CPS Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Minutes)
Line 23: Line 23:
 
== Minutes ==
 
== Minutes ==
 
* Reviewed minutes from last meeting
 
* Reviewed minutes from last meeting
 +
* Translation from NX to Fluka were largely unsuccessful
 +
* Need to give x, y and z coordinates of shielding around the absorber to Pavel to rerun Fluka model (Keith H.)
 +
* Get Pavel magnet dimensions to rerun Fluka (Stephanie)
 +
* Discussed use of air casters to move the CPS assy around during installation and moving after commissioning
 +
** About $35K to procure system
 +
** It will give us much ore flexibility during assembly
 +
** Need to rent a portable compressor (200 SCFM) with 2" air lines
 +
** seemed to be acceptable plan, we will pursue this further
 +
** Concerns with radioactive dust (contamination)
 +
** Get with ES&H/RADCON to discuss mitigations
 +
** Will see if anyone else at the lab has used this or owns a system - no go
 +
* Discussed Project Gant chart being developed for the entire KLONG project -
 +
** will send a preliminary out soon (Tim)
 +
** Will include schedule and manpower needs
 +
** Keith H. will most likely have less time in the near future to work on KLONG
 +
* Pavel to rerun model to
  
 
== Action Items ==
 
== Action Items ==

Revision as of 13:04, 25 April 2024

Meeting Time and Place

Tuesday, April 23, 2024, 1:15pm Hall D Counting House

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard

Agenda

Minutes

  • Reviewed minutes from last meeting
  • Translation from NX to Fluka were largely unsuccessful
  • Need to give x, y and z coordinates of shielding around the absorber to Pavel to rerun Fluka model (Keith H.)
  • Get Pavel magnet dimensions to rerun Fluka (Stephanie)
  • Discussed use of air casters to move the CPS assy around during installation and moving after commissioning
    • About $35K to procure system
    • It will give us much ore flexibility during assembly
    • Need to rent a portable compressor (200 SCFM) with 2" air lines
    • seemed to be acceptable plan, we will pursue this further
    • Concerns with radioactive dust (contamination)
    • Get with ES&H/RADCON to discuss mitigations
    • Will see if anyone else at the lab has used this or owns a system - no go
  • Discussed Project Gant chart being developed for the entire KLONG project -
    • will send a preliminary out soon (Tim)
    • Will include schedule and manpower needs
    • Keith H. will most likely have less time in the near future to work on KLONG
  • Pavel to rerun model to

Action Items