Difference between revisions of "Bill's to do list"

From GlueXWiki
Jump to: navigation, search
(2020 Summer DIRC To-do List)
(2020 Summer DIRC To-do List)
Line 34: Line 34:
  
 
==2020 Summer DIRC To-do List==
 
==2020 Summer DIRC To-do List==
# Water level sensor installation
+
# Hall work:
# Darkening leak check
+
#* Water level sensor installation (Total:  2 days. 1 day testing + 1 day installation)
# Modification on vent exit to reduce FPGA temperature
+
#* Darkening leak check (1 day)
 +
#* Modification on vent exit to reduce FPGA temperature (Total: 3 days. 1 day diagnose, 1 day test and 1 day installation)
 +
#* DIRC Diffuser seal issue
 +
#** North LED 2 replacement
 +
#** Water test fixture
 +
#* Control and operation
 +
#** Alarm modification strategy 
 +
#** Resolving (double checking) DIRC hole in occupancy before run starts
 +
#** Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
 +
#** Individual (stand alone) SiPM TDA offset
 +
#* contaminated mirror replacement
 +
#* Recover loan-out (Duke SOLID group) MOROC chips
 +
#* Tile FPGA voltage regulation issue.
 +
 
 
# Testing spare DIRC modules
 
# Testing spare DIRC modules
# DIRC Diffuser seal issue
 
#* North LED 2 replacement
 
#* Water test fixture
 
# Control and operation
 
#* Alarm modification strategy 
 
#* Resolving (double checking) DIRC hole in occupancy before run starts
 
#* Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
 
#* Individual (stand alone) SiPM TDA offset
 
# contaminated mirror replacement
 
# Recover loan-out (Duke SOLID group) MOROC chips
 
# Tile FPGA voltage regulation issue.
 

Revision as of 13:38, 10 April 2020

2018

  1. Priority list:
    • Laser alignment and generating mis-alignment table (Bill, Andrew).
    • Feedthrough opening angle measurement and fish tank (Bill, Fernando).
    • Light monitors testing and mounting (Bill, Keith).
    • DIRC module cabling strategy (Bill/Andrew).
    • Hole opening on the backplate (Keith).
    • Hole opening on the of the PMT mounting plate (Tim, Keith, Bobby).
    • Plastic bolts and screws for the FPGA board. (Chris)
    • Recover PMT #9 and 10 and perform test
    • Spare micro-BNC cable for the big box. (Omen)
    • Cleaning of the mirrors. (Greg, Keith)
    • Remarking and repositioning the Fiber cable label. (Fernando/Chris)
    • PMT mounting plate spacer (Bobby)
    • Installation tray. (Mark/Keith)
    • Installation spacer. (Bobby)

2019

  1. Temperature reduction for the DIRC FPGAs.
  2. Water quality setup, 3D printing the box.
  3. Darkening.
  4. Uni-strut reinforcement for the distribution boxes.
  5. Airflow sensor
  6. Opening both DIRC boxes in January:
    • Check mirror quality
    • Check anodize quality
    • Check water tightness of the diffuser assembly.
  7. North Box:
    • Check corner interference.
    • Silicone around the wielding spot.
  8. South Box:
    • Check the chipped corner water seal for both spots

2020 Summer DIRC To-do List

  1. Hall work:
    • Water level sensor installation (Total: 2 days. 1 day testing + 1 day installation)
    • Darkening leak check (1 day)
    • Modification on vent exit to reduce FPGA temperature (Total: 3 days. 1 day diagnose, 1 day test and 1 day installation)
    • DIRC Diffuser seal issue
      • North LED 2 replacement
      • Water test fixture
    • Control and operation
      • Alarm modification strategy
      • Resolving (double checking) DIRC hole in occupancy before run starts
      • Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
      • Individual (stand alone) SiPM TDA offset
    • contaminated mirror replacement
    • Recover loan-out (Duke SOLID group) MOROC chips
    • Tile FPGA voltage regulation issue.
  1. Testing spare DIRC modules