Difference between revisions of "Coil Test Weekly Meeting 11Feb-2010"
From GlueXWiki
m |
m |
||
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
− | * Supplying EPICS values to PLC | + | * Supplying EPICS values to PLC via Linux computer - Elliott |
* Behavior of power supply after brief power loss and reestablishing coil current - Elliott | * Behavior of power supply after brief power loss and reestablishing coil current - Elliott | ||
* What goes into fourth controls rack - Scot | * What goes into fourth controls rack - Scot |
Latest revision as of 09:39, 11 February 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 11-Feb-2010 9:45 am ARC 428
Agenda
- Supplying EPICS values to PLC via Linux computer - Elliott
- Behavior of power supply after brief power loss and reestablishing coil current - Elliott
- What goes into fourth controls rack - Scot
- EWEB module - Elliott
- Report on safety meeting, final P&I diagram, machine protection, failure scenarios - Josh
- Status of PLC programming - Mark W
- Wiring progress in F117 - Scot
- Status of items on George's punch list - George
- Do we want to tie into existing vent piping system - Mark S, Scot
- What PLC display pages do we want, and what should be archived and how often - George
- main pages, fault pages, trends, etc.
- Coil 1 cryostat testing status - George
- Coil 1 status - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Backup computer - Elliott
- Safety reviews, formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items