Line 11: | Line 11: | ||
* DOE review 28-Sep - George, Elliott | * DOE review 28-Sep - George, Elliott | ||
** final status for Glenn's talk | ** final status for Glenn's talk | ||
− | + | * Conduct of Operations - Josh, Elliott | |
+ | ** results of Wed meeting | ||
* OSP documents and review - Elliott, George | * OSP documents and review - Elliott, George | ||
** what is left to do? | ** what is left to do? |
Revision as of 08:52, 20 September 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 23-Sep-2010 9:30am ARC 428
Agenda
- DOE review 28-Sep - George, Elliott
- final status for Glenn's talk
- Conduct of Operations - Josh, Elliott
- results of Wed meeting
- OSP documents and review - Elliott, George
- what is left to do?
- when can/must we turn everything in?
- Installation status
- what's left?
- when do we give two weeks notice to Errol?
- Test plan - Josh
- Magnet power supply and interlock commissioning - Cody
- latest status
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer?
- tutorial?
- EPICS <--> PLC communications - Wesley
- PV list from Jonathan Creel
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- Josh's screens
- current status
- tutorial?
- Coil repair status - George
- Preparations for testing next coil - George, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring