=== Tagger Microscope ===
 
=== Tagger Microscope ===
* <font color="darkred"><b><i>10/03/2011    -  04/13/2012</i></b></font>  -  Procument Fibers for Microscope
+
* <font color="darkred"><b><i>10/03/2011    -  04/13/2012</i></b></font>  -  Procument Fibers for Microscope ($11,905)
* <font color="darkred"><b><i>12/02/2011    -  06/14/2012</i></b></font>  -  Procument SiPMs for Microscope
+
* <font color="darkred"><b><i>12/02/2011    -  06/14/2012</i></b></font>  -  Procument SiPMs for Microscope   ($136,060)
 +
* <font color="darkred"><b><i>10/03/2011    -  05/25/2012</i></b></font>    -  Design and Layout Preamplifier Board
 +
* <font color="darkgreen"><b><i>06/15/2012  -  05/03/2013</i></b></font>  -  Fabricate Counters Microscope ($26,470 labor)
 +
* <font color="darkgreen"><b><i>10/01/2012  -  15/03/2013</i></b></font>  -  Manufacture Base/Preamplifier Board ($24,365)
  
 
=== Fixed Array Hodoscope ===
 
=== Fixed Array Hodoscope ===
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument Scintillator/Light Guide for Fixed Array
+
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument Scintillator/Light Guide for Fixed Array ($7,871)
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument PMTs for Fixed Array
+
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument PMTs for Fixed Array ($51,589)
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument Dividers for Fixed Array
+
* <font color="darkred"><b><i>01/05/2012    -  07/10/2012</i></b></font>  -  Procument Dividers for Fixed Array ($30,636)
 
* <font color="darkgreen"><b><i>03/08/2012  -  06/08/2012</i></b></font>  -  Fabricate and Test Fixed Array Counter
 
* <font color="darkgreen"><b><i>03/08/2012  -  06/08/2012</i></b></font>  -  Fabricate and Test Fixed Array Counter

Latest revision as of 17:10, 4 January 2012

Active Collimator

  • 01/05/2012 - 07/10/2012 - Procument Active Collimator Components
  • 07/11/2012 - 01/23/2013 - Assemble Active Collimator
  • 07/11/2012 - 12/14/2012 - Program and Test Collimator Table
  • 01/23/2013 - 04/24/2013 - Test Active Collimator

Tagger Microscope

  • 10/03/2011 - 04/13/2012 - Procument Fibers for Microscope ($11,905)
  • 12/02/2011 - 06/14/2012 - Procument SiPMs for Microscope ($136,060)
  • 10/03/2011 - 05/25/2012 - Design and Layout Preamplifier Board
  • 06/15/2012 - 05/03/2013 - Fabricate Counters Microscope ($26,470 labor)
  • 10/01/2012 - 15/03/2013 - Manufacture Base/Preamplifier Board ($24,365)

Fixed Array Hodoscope

  • 01/05/2012 - 07/10/2012 - Procument Scintillator/Light Guide for Fixed Array ($7,871)
  • 01/05/2012 - 07/10/2012 - Procument PMTs for Fixed Array ($51,589)
  • 01/05/2012 - 07/10/2012 - Procument Dividers for Fixed Array ($30,636)
  • 03/08/2012 - 06/08/2012 - Fabricate and Test Fixed Array Counter