Original Plan
- August 22 to October 28 9.5 Weeks of Running Complete GlueX Phase I
- October 29 to November 19 3 Weeks Installation of CompCal and DIRC
- November 19 to December 19 4 Weeks CompCal and DIRC Commissioning
Modified Plan at Collaboration Meeting
- September 28 to November 10 6 Weeks GlueX Phase I
- November 11 to November 25 2 Weeks CompCal Installation (DIRC Installation as possible)
- November 26 to December 19 3 Weeks CompCal Commissioning