(Created page with "== Action Items from previous meetings == # Populate interface cards to the ADC (Chris) # Complete 3 remaining boards for SiPM testing (Chris) # Determine if swapped bias pins w...")
 
(Action Items from previous meetings)
Line 6: Line 6:
 
# Modify design so that the samtek/ADC transition board the locking mechanism works (Chris)
 
# Modify design so that the samtek/ADC transition board the locking mechanism works (Chris)
 
# Provide cost information to Chris regarding the thermistor (Jack)
 
# Provide cost information to Chris regarding the thermistor (Jack)
# <strike> Check to see if files sent from Athens can be read (Jim/Chris) </strike> Yes.
+
# Make a second SiPM extraction tool for USM (Jim and Scot)
  
 
== Tentative Agenda ==
 
== Tentative Agenda ==

Revision as of 18:46, 2 February 2012

Action Items from previous meetings

  1. Populate interface cards to the ADC (Chris)
  2. Complete 3 remaining boards for SiPM testing (Chris)
  3. Determine if swapped bias pins was accidental or in design (Chris)
  4. Modify design so that the samtek/ADC transition board the locking mechanism works (Chris)
  5. Provide cost information to Chris regarding the thermistor (Jack)
  6. Make a second SiPM extraction tool for USM (Jim and Scot)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
  5. Mechanical assembly (Scot)
  6. Mechanical (Jim)
  7. Mechanical drawings (Chuck)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Fernando/Chris)
  10. SiPM testing (Ivan)

Minutes

Attending: