Difference between revisions of "For the third coil"
From GlueXWiki
m |
m |
||
Line 13: | Line 13: | ||
* Danfysik power supply | * Danfysik power supply | ||
− | ** fix broken transistor | + | ** fix broken transistor - '''done 20-Apr-2011''' |
** commission fault sequencer | ** commission fault sequencer | ||
** fix slow dump | ** fix slow dump |
Revision as of 14:50, 21 April 2011
To-do list
- Wiring
- rewire for coil 3 subcoils
- 20 kOhm protection resistors for coil taps if needed for quench detector balancing - not needed 7-Apr-2011
- eliminiate pickup on downstream lead/splice and other channels (esp. during dump)
- understand induced voltages on taps during testing
- understand noise, signal clipping and interaction between modules
- document trip chains
- label circuit breakers
- Danfysik power supply
- fix broken transistor - done 20-Apr-2011
- commission fault sequencer
- fix slow dump
- understand ramp-down mechanism
- understand varying fast dump time constant - Possibly understood 8-Apr-2011, needs verification
- choose ground fault detection mechanism
- cover holes in cabinet - done 8-Apr-2011
- Danfysik quench detector
- install bias pot on remaining three channels - done 7-Apr-2011
- implement divider circuit upstream of QD to eliminate effect of coil imbalances - not needed 7-Apr-2011
- install trip test points
- Instrumentation
- ensure all devices on clean power with good grounds - done 8-apr-2011
- check out Newport controllers, flow switch, replace if needed
- implement system to isolate fault detectors and determine time sequence of trips - Postponed 8-Apr-2011
- understand spikes on shunt Newport
- understand effect of B field on all sensors, move devices if needed
- monitor circuit breakers?
- NI USB device - replaced by VME DAQ system 7-Apr-2011
- rework Zener/divider box, needs to be fully bipolar
- eliminate noise
- VME-based fast DAQ
- get hardware, test in lab - done 7-Apr-2011
- write software, test in lab
- connect to apparatus
- commission
- A-B HMI improvements
- upgrade to 100 screen license
- implement fault sequence screens if system implemented - Not implemented 8-Apr-2011
- A-B PLC program improvements
- EPICS
- EWEB screens
- update for latest tags and drawings
- Auxiliary tests
- requirements, setup for aux tests
For the hall
- note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
- should we install a UPS on the Danfysik contactor and control boards?
- should we install a second contactor in the Danfysik power supply?
- do we need additional valves, check valves, bypasses, whatever?
- do we need Dataforth voltage attenuators on coil tap channels?
- do we need active isolation of coil tap channels, etc?
- should we monitor all circuit breakers?
- should we monitor all relays?
- what is the effect of B field on sensors/relays? should some instrumentation be relocated?
- do we need new flow sensors, or should they be relocated?
- lock box for power supply key
- more ethernet power strips
- use custom ("add-on") instructions to simplify PLC code