Difference between revisions of "For the third coil"

From GlueXWiki
Jump to: navigation, search
m
m
Line 3: Line 3:
  
 
* Wiring
 
* Wiring
** rewire for coil 3 subcoils
+
** rewire for coil 3 subcoils - ...done 25-Apr-2011'''
 
** 20 kOhm protection resistors for coil taps if needed for quench detector balancing - '''not needed 7-Apr-2011'''
 
** 20 kOhm protection resistors for coil taps if needed for quench detector balancing - '''not needed 7-Apr-2011'''
** eliminiate pickup on downstream lead/splice and other channels (esp. during dump)
 
** understand induced voltages on taps during testing
 
** understand noise, signal clipping and interaction between modules
 
 
** document trip chains
 
** document trip chains
 
** label circuit breakers
 
** label circuit breakers
Line 30: Line 27:
 
* Instrumentation
 
* Instrumentation
 
** ensure all devices on clean power with good grounds - '''done 8-apr-2011'''
 
** ensure all devices on clean power with good grounds - '''done 8-apr-2011'''
** check out Newport controllers, flow switch, replace if needed
+
** check out Newport controllers, flow switch, replace if needed - '''done 25-apr-2011'''
 
** implement system to isolate fault detectors and determine time sequence of trips - '''Postponed 8-Apr-2011'''
 
** implement system to isolate fault detectors and determine time sequence of trips - '''Postponed 8-Apr-2011'''
 
** understand spikes on shunt Newport
 
** understand spikes on shunt Newport
Line 44: Line 41:
 
* VME-based fast DAQ
 
* VME-based fast DAQ
 
** get hardware, test in lab - '''done 7-Apr-2011'''
 
** get hardware, test in lab - '''done 7-Apr-2011'''
** write software, test in lab
+
** write software, test in lab - '''done 25-Apr-2011'''
** connect to apparatus
+
** connect to apparatus - '''done 25-Apr-2011'''
 
** commission
 
** commission
  
Line 67: Line 64:
 
** requirements, setup for aux tests
 
** requirements, setup for aux tests
  
 +
 +
* Reenable cron job
 +
** when cooldown commences, end when warmed up
  
  

Revision as of 13:08, 28 April 2011

To-do list


  • Wiring
    • rewire for coil 3 subcoils - ...done 25-Apr-2011
    • 20 kOhm protection resistors for coil taps if needed for quench detector balancing - not needed 7-Apr-2011
    • document trip chains
    • label circuit breakers


  • Danfysik power supply
    • fix broken transistor - done 20-Apr-2011
    • commission fault sequencer
    • fix slow dump
    • understand ramp-down mechanism
    • understand varying fast dump time constant - Possibly understood 8-Apr-2011, needs verification
    • choose ground fault detection mechanism
    • cover holes in cabinet - done 8-Apr-2011


  • Danfysik quench detector
    • install bias pot on remaining three channels - done 7-Apr-2011
    • implement divider circuit upstream of QD to eliminate effect of coil imbalances - not needed 7-Apr-2011
    • install trip test points


  • Instrumentation
    • ensure all devices on clean power with good grounds - done 8-apr-2011
    • check out Newport controllers, flow switch, replace if needed - done 25-apr-2011
    • implement system to isolate fault detectors and determine time sequence of trips - Postponed 8-Apr-2011
    • understand spikes on shunt Newport
    • understand effect of B field on all sensors, move devices if needed
    • monitor circuit breakers?


  • NI USB device - replaced by VME DAQ system 7-Apr-2011
    • rework Zener/divider box, needs to be fully bipolar
    • eliminate noise


  • VME-based fast DAQ
    • get hardware, test in lab - done 7-Apr-2011
    • write software, test in lab - done 25-Apr-2011
    • connect to apparatus - done 25-Apr-2011
    • commission


  • A-B HMI improvements
    • upgrade to 100 screen license
    • implement fault sequence screens if system implemented - Not implemented 8-Apr-2011


  • A-B PLC program improvements


  • EPICS


  • EWEB screens
    • update for latest tags and drawings


  • Auxiliary tests
    • requirements, setup for aux tests


  • Reenable cron job
    • when cooldown commences, end when warmed up


For the hall

  • note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
  • should we install a UPS on the Danfysik contactor and control boards?
  • should we install a second contactor in the Danfysik power supply?
  • do we need additional valves, check valves, bypasses, whatever?
  • do we need Dataforth voltage attenuators on coil tap channels?
  • do we need active isolation of coil tap channels, etc?
  • should we monitor all circuit breakers?
  • should we monitor all relays?
  • what is the effect of B field on sensors/relays? should some instrumentation be relocated?
  • do we need new flow sensors, or should they be relocated?
  • lock box for power supply key
  • more ethernet power strips
  • use custom ("add-on") instructions to simplify PLC code