Difference between revisions of "For the third coil"

From GlueXWiki
Jump to: navigation, search
m
m
Line 30: Line 30:
 
** check out Newport controllers, flow switch, replace if needed - '''done 25-apr-2011'''
 
** check out Newport controllers, flow switch, replace if needed - '''done 25-apr-2011'''
 
** implement system to isolate fault detectors and determine time sequence of trips - '''Postponed 8-Apr-2011'''
 
** implement system to isolate fault detectors and determine time sequence of trips - '''Postponed 8-Apr-2011'''
** understand spikes on shunt Newport
+
** understand spikes on shunt Newport - '''May never understand these...'''
** understand effect of B field on all sensors, move devices if needed
+
** understand effect of B field on all sensors, move devices if needed - '''Devices moved 8-Apr-2011'''
 
** monitor circuit breakers?
 
** monitor circuit breakers?
  
Line 48: Line 48:
  
 
* A-B HMI improvements
 
* A-B HMI improvements
** upgrade to 100 screen license
+
** upgrade to 100 screen license - '''done 6-May-2011'''
 
** implement fault sequence screens if system implemented - '''Not implemented 8-Apr-2011'''
 
** implement fault sequence screens if system implemented - '''Not implemented 8-Apr-2011'''
  
Line 63: Line 63:
  
 
* Auxiliary tests
 
* Auxiliary tests
** requirements, setup for aux tests
+
** requirements, setup for aux tests - '''done 12-May-2011'''
  
  
 
* Reenable cron job
 
* Reenable cron job
** when cooldown commences, end when warmed up
+
** when cooldown commences, end when warmed up - '''done 1-May-2011'''
  
  

Revision as of 09:44, 12 May 2011

To-do list


  • Wiring
    • rewire for coil 3 subcoils - ...done 25-Apr-2011
    • 20 kOhm protection resistors for coil taps if needed for quench detector balancing - not needed 7-Apr-2011
    • document trip chains
    • label circuit breakers


  • Danfysik power supply
    • add new readout channels - done 25-apr-2011
    • fix broken transistor - done 20-Apr-2011
    • commission fault sequencer
    • fix slow dump
    • understand ramp-down mechanism
    • understand varying fast dump time constant - Possibly understood 8-Apr-2011, needs verification
    • choose ground fault detection mechanism
    • cover holes in cabinet - done 8-Apr-2011


  • Danfysik quench detector
    • install bias pot on remaining three channels - done 7-Apr-2011
    • implement divider circuit upstream of QD to eliminate effect of coil imbalances - not needed 7-Apr-2011
    • install trip test points


  • Instrumentation
    • ensure all devices on clean power with good grounds - done 8-apr-2011
    • check out Newport controllers, flow switch, replace if needed - done 25-apr-2011
    • implement system to isolate fault detectors and determine time sequence of trips - Postponed 8-Apr-2011
    • understand spikes on shunt Newport - May never understand these...
    • understand effect of B field on all sensors, move devices if needed - Devices moved 8-Apr-2011
    • monitor circuit breakers?


  • NI USB device - replaced by VME DAQ system 7-Apr-2011
    • rework Zener/divider box, needs to be fully bipolar
    • eliminate noise


  • VME-based fast DAQ
    • get hardware, test in lab - done 7-Apr-2011
    • write software, test in lab - done 25-Apr-2011
    • connect to apparatus - done 25-Apr-2011
    • commission


  • A-B HMI improvements
    • upgrade to 100 screen license - done 6-May-2011
    • implement fault sequence screens if system implemented - Not implemented 8-Apr-2011


  • A-B PLC program improvements


  • EPICS


  • EWEB screens
    • update for latest tags and drawings


  • Auxiliary tests
    • requirements, setup for aux tests - done 12-May-2011


  • Reenable cron job
    • when cooldown commences, end when warmed up - done 1-May-2011


For the hall

  • note that max ramp rate in the hall is approximately 10V / 20H = 0.5 A/sec
  • should we install a UPS on the Danfysik contactor and control boards?
  • should we install a second contactor in the Danfysik power supply?
  • do we need additional valves, check valves, bypasses, whatever?
  • do we need Dataforth voltage attenuators on coil tap channels?
  • do we need active isolation of coil tap channels, etc?
  • should we monitor all circuit breakers?
  • should we monitor all relays?
  • what is the effect of B field on sensors/relays? should some instrumentation be relocated?
  • do we need new flow sensors, or should they be relocated?
  • lock box for power supply key
  • more ethernet power strips
  • use custom ("add-on") instructions to simplify PLC code