GlueX Start Counter Meeting<br>
 
GlueX Start Counter Meeting<br>
Thursday, June 27, 2013<br>
+
Thursday, August 8, 2013<br>
 
10 am EDT<br>
 
10 am EDT<br>
 
JLab: CEBAF Center F326/327
 
JLab: CEBAF Center F326/327
Line 7: Line 7:
  
 
# Announcements
 
# Announcements
# Review [[GlueX Start Counter Meeting, June 27, 2013#Minutes|minutes from previous meeting]]
+
# Review [[GlueX Start Counter Meeting, July 25, 2013#Minutes|minutes from previous meeting]]
# Chuck's Start Counter Drawings: see the slides directory
+
 
# Construction Status
 
# Construction Status
 
# Contract
 
# Contract
 +
# Installation planning
  
 
=Communication Information=
 
=Communication Information=
Line 35: Line 35:
 
==Slides==
 
==Slides==
  
Talks can be deposited in the directory <code>/group/halld/www/halldweb1/html/talks/2013-3Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2013-3Q/ .
+
Talks can be deposited in the directory <code>/group/halld/www/halldweb/html/talks/2013-3Q</code> on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2013-3Q/ .
 +
 
 +
=Minutes=
 +
 
 +
Present:
 +
* '''FIU''': Lei Guo, Eric Pooser
 +
* '''JLab''': Chuck Hutton, Mark Ito (chair), Tim Whitlatch, Beni Zihlmann
 +
 
 +
==Review of Minutes from Previous Meeting==
 +
 
 +
We looked at the [[GlueX Start Counter Meeting, July 25, 2013#Minutes|minutes from the July 25th meeting]], chaired by Beni.
 +
 
 +
Eric told us that the test stand will be ready by September 9th at the latest. The machine shop at FIU has been very busy.
 +
 
 +
==Construction Status==
 +
 
 +
Eric has re-measured paddles 1, 2, and 3 from the latest batch, now 7 weeks after the initial measurements. These paddles had been handled with the aloe-coated gloves and now in fact show some localized crazing in areas where the counters were handled, especially along edges and the nose. He showed [https://halldweb.jlab.org/talks/2013-3Q/Second_Measurement_Paddle_123.pdf plots] with time resolution and attenuation length for these paddles. They show some deterioration of resolution, but only from the nose section. Paddles 4 and 5 were not handled with the gloves. They will be measured by the end of the week. Eric will update his slides to include those measurements.
 +
 
 +
==Contract==
 +
 
 +
FIU has started purchasing small items under the contract.
 +
 
 +
==Foam Support Material==
 +
 
 +
The [http://www.generalplastics.com/products/rigid-foams/ Last-A-Foam] product from General Plastics that Hall B used for its start counter comes in a wide variety of types and densities within each type. Mark talked to Youri Sharabian and Doug Tilles of Hall B and was told that Steve Christo is their Last-A-Foam guru. Chuck will consult with Steve on the best product for our purposes.

Latest revision as of 06:35, 1 April 2015

GlueX Start Counter Meeting
Thursday, August 8, 2013
10 am EDT
JLab: CEBAF Center F326/327

Agenda

  1. Announcements
  2. Review minutes from previous meeting
  3. Construction Status
  4. Contract
  5. Installation planning

Communication Information

Video Conferencing

  • ESNet: 8542553
  • SeeVogh
    • Direct meeting link
    • Phone Bridge ID: 15 4136

Telephone

  1. Dial
  2. enter access code followed by the # sign: 1833622#

Desktop Sharing

  1. Go to http://esnet.readytalk.com
  2. In the "join a meeting" box enter the Hall D code: 1833622
  3. Fill in the participant registration form.

Slides

Talks can be deposited in the directory /group/halld/www/halldweb/html/talks/2013-3Q on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2013-3Q/ .

Minutes

Present:

  • FIU: Lei Guo, Eric Pooser
  • JLab: Chuck Hutton, Mark Ito (chair), Tim Whitlatch, Beni Zihlmann

Review of Minutes from Previous Meeting

We looked at the minutes from the July 25th meeting, chaired by Beni.

Eric told us that the test stand will be ready by September 9th at the latest. The machine shop at FIU has been very busy.

Construction Status

Eric has re-measured paddles 1, 2, and 3 from the latest batch, now 7 weeks after the initial measurements. These paddles had been handled with the aloe-coated gloves and now in fact show some localized crazing in areas where the counters were handled, especially along edges and the nose. He showed plots with time resolution and attenuation length for these paddles. They show some deterioration of resolution, but only from the nose section. Paddles 4 and 5 were not handled with the gloves. They will be measured by the end of the week. Eric will update his slides to include those measurements.

Contract

FIU has started purchasing small items under the contract.

Foam Support Material

The Last-A-Foam product from General Plastics that Hall B used for its start counter comes in a wide variety of types and densities within each type. Mark talked to Youri Sharabian and Doug Tilles of Hall B and was told that Steve Christo is their Last-A-Foam guru. Chuck will consult with Steve on the best product for our purposes.