Difference between revisions of "GlueX Target Meeting, June 24, 2014"

From GlueXWiki
Jump to: navigation, search
Line 23: Line 23:
 
** Spare cell
 
** Spare cell
 
* Schedule
 
* Schedule
** Readiness review
+
** Readiness review [[Media:Target Review.pdf]]
 
** Assy/test in EEL
 
** Assy/test in EEL
 
** Install/test in Hall
 
** Install/test in Hall
Line 36: Line 36:
  
 
==Minutes==
 
==Minutes==
 
* James fabricating new cell with straight torlon base and aluminized Kapton(plus a spare) - parts due in this week
 
* Target group fabricating an interlock box to hard wire turn off the compressor - Dave Griffith
 
* Ok to put kill button in counting room for Target
 
* (2) 55 gallon Tanks are in
 
* Target group will procure one additional relief valve - 1 relief on each tank and 2 on gas panel
 
* Vent stack materials defined and on order - Hall D to assemble
 
* Joe Beaufeit to verify compressor power and ensure it is supplied in Hall D
 
* May 8th safety review - Tim to send proposal to Patrizia for agenda and pre-brief
 
* 5mil kapton window between target and upstream beamline is acceptable
 
* 4" gate valve (on order) and turbo for pumping on vacuum chamber and 1.5" valve on beamline (both in house) supplied by Hall D
 
* Target group will supply a diaphragm switch hard wired to turn turbo off
 
* Tim/Mark to meet with Fernando to determine start counter cabling/patch panel config.
 
* Vacuum chamber bottom flange to include 4" pump port and 4 - 2 3/4" conflat ports on order (Matt to check with Dave Meekins if class C ok)
 
* Chris sent email to Javier outlining responsibilities
 
* Hall D will deliver assembled cart to target group this week. It will have mounts for tanks but the target adjustment cartridges will not be available until next week
 
* Tim will get with Jim Dahlberg for more detail on fiducial points.
 
* Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor
 
* Need to look at required spares some day - Chris working
 
* Target group will buy vacuum instrumentation
 
* need to move 4" gate valve downstream and add tee for vacuum instrumentation
 
* James pointed out that a cover for the scattering chamber will be needed when removed from position
 
* Werth from the detector group is helping Dave B. with the controls
 
* Need to control start/stop of compressor (Werth to look at Labview setup)
 
* there will be a 20' long flexible gas line from the target to the vent line
 
* Chris to supply list of signal names to Dave by the end of the week.
 
* Discussion on location of controls crate and magnetic field magnitude - Tim to develop location vs. mag field layouts to help make the decision on the final location for the controls.
 
* Need to fit check Start counter hub to target hub next week to ensure proper mating
 

Revision as of 11:32, 24 June 2014

Present: Chris Keith, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch

Minutes from last mtg https://halldweb1.jlab.org/wiki/index.php/GlueX_Target_Design_Mtg,_April_21,_2014

Agenda

  • Where are we now? Media:Target labor.pdf
  • Gas system status
    • Exhaust from pressure relief
    • Plumbing on cart
    • pressure system documentation
    • Storage tanks
  • 3D model/drawings Media:Target assy.pdf
  • Vacuum system
  • Controls status
    • updated P&I
    • changes for subcooled config
  • Cart mods
    • Controls/panel config
    • Alignment
  • Scattering chamber status
  • Cell Fabrication Status
    • thermometry
    • Spare cell
  • Schedule