|
|
Line 23: |
Line 23: |
| ** Spare cell | | ** Spare cell |
| * Schedule | | * Schedule |
− | ** Readiness review | + | ** Readiness review [[Media:Target Review.pdf]] |
| ** Assy/test in EEL | | ** Assy/test in EEL |
| ** Install/test in Hall | | ** Install/test in Hall |
Line 36: |
Line 36: |
| | | |
| ==Minutes== | | ==Minutes== |
− |
| |
− | * James fabricating new cell with straight torlon base and aluminized Kapton(plus a spare) - parts due in this week
| |
− | * Target group fabricating an interlock box to hard wire turn off the compressor - Dave Griffith
| |
− | * Ok to put kill button in counting room for Target
| |
− | * (2) 55 gallon Tanks are in
| |
− | * Target group will procure one additional relief valve - 1 relief on each tank and 2 on gas panel
| |
− | * Vent stack materials defined and on order - Hall D to assemble
| |
− | * Joe Beaufeit to verify compressor power and ensure it is supplied in Hall D
| |
− | * May 8th safety review - Tim to send proposal to Patrizia for agenda and pre-brief
| |
− | * 5mil kapton window between target and upstream beamline is acceptable
| |
− | * 4" gate valve (on order) and turbo for pumping on vacuum chamber and 1.5" valve on beamline (both in house) supplied by Hall D
| |
− | * Target group will supply a diaphragm switch hard wired to turn turbo off
| |
− | * Tim/Mark to meet with Fernando to determine start counter cabling/patch panel config.
| |
− | * Vacuum chamber bottom flange to include 4" pump port and 4 - 2 3/4" conflat ports on order (Matt to check with Dave Meekins if class C ok)
| |
− | * Chris sent email to Javier outlining responsibilities
| |
− | * Hall D will deliver assembled cart to target group this week. It will have mounts for tanks but the target adjustment cartridges will not be available until next week
| |
− | * Tim will get with Jim Dahlberg for more detail on fiducial points.
| |
− | * Hall D to supply cooling water for compressor and temp sensors, target group to supply return flow instrumentation. Need to set turn off temps for compressor
| |
− | * Need to look at required spares some day - Chris working
| |
− | * Target group will buy vacuum instrumentation
| |
− | * need to move 4" gate valve downstream and add tee for vacuum instrumentation
| |
− | * James pointed out that a cover for the scattering chamber will be needed when removed from position
| |
− | * Werth from the detector group is helping Dave B. with the controls
| |
− | * Need to control start/stop of compressor (Werth to look at Labview setup)
| |
− | * there will be a 20' long flexible gas line from the target to the vent line
| |
− | * Chris to supply list of signal names to Dave by the end of the week.
| |
− | * Discussion on location of controls crate and magnetic field magnitude - Tim to develop location vs. mag field layouts to help make the decision on the final location for the controls.
| |
− | * Need to fit check Start counter hub to target hub next week to ensure proper mating
| |
Present: Chris Keith, Josh Pierce, James Brock, Matt Marchlik, Dave Butler, Alexandre Deur, Tim Whitlatch