* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
** Fabricated modules: <span style="color:#FF0000"> Total 1482 </span>
+
** Fabricated modules: <span style="color:#FF0000"> Total 1487 </span>
**: Currently available for fabrication: 17  (modules will be available during next week)
+
**: Available for fabrication: 26
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication.pdf All SICCAS 576 + 3 SICCAS] -->
+
**: Fabricate 36 modules from 'low quality' crystals for stacking mockup and 'crash' tests (train students on them)
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/module_fabrication_crytur.pdf 834 CRYTUR], available: 1 -->
+
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad / Arshak
<!-- *** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/11_11_22 Moving modules to the new lab (EEL108)] -->
+
* '''[[Testing of PMT dividers]]''' -- Sasha / Arshak
+
 
** FCAL2 modules with dividers installed on the CCAL [https://logbooks.jlab.org/entry/4140983]
 
** FCAL2 modules with dividers installed on the CCAL [https://logbooks.jlab.org/entry/4140983]
 
** Meeting with Vlad P. on Tuesday next week (final check of the dividers, proceed with the order)
 
** Meeting with Vlad P. on Tuesday next week (final check of the dividers, proceed with the order)

Revision as of 09:09, 28 April 2023

Meeting time and location:

  • 9:30 am EST (JLab time) remote only
  • Zoom meeting ID: 161 050 9142 Passcode: 004965

Agenda

  • Preparation of parts for FCAL2 modules -- Sasha
    • Crystals:
      10 CRYTUR crystals (out of 95 [1] ) were sent to us last week
      All crystals from the CCAL prototype were removed
      26 crystals were wrapped by Mindy
      Number of available crystals: 1487 (modules) + 26 = 1513, expect to receive 95 from CRYTUR: 1513 + 95 = 1608 (12 spares)
    • George (DSG group) unwrapped CCAL modules and removed LMS caps. Preshaped 48 ESR reflectors, have to preshape 32 more.
    • More than 200 long signal cables received, can start checking, bundling, labeling
    • Procurement parts for the LMS
      Ordered 16,000 ft of optical fibers. Expect that they will be delivered in May. Adding additional 8000 ft to the PO
      Ordered 18000 of polycarbonate donats
  • Module fabrication -- Sasha
    • Fabricated modules: Total 1487
      Available for fabrication: 26
      Fabricate 36 modules from 'low quality' crystals for stacking mockup and 'crash' tests (train students on them)
  • Testing of PMT dividers -- Sasha / Vlad / Arshak
    • FCAL2 modules with dividers installed on the CCAL [2]
    • Meeting with Vlad P. on Tuesday next week (final check of the dividers, proceed with the order)
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak
Discussion of the FCAL2 installation procedures [4]