Difference between revisions of "JEF meeting, August 25, 2023"

From GlueXWiki
Jump to: navigation, search
(Created page with "Meeting time and location: *9:30 am EST (JLab time) remote only * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection inform...")
 
(Agenda)
Line 4: Line 4:
  
 
=Agenda=
 
=Agenda=
 +
  
 
*'''Preparation of parts for ECAL modules''' -- Sasha  
 
*'''Preparation of parts for ECAL modules''' -- Sasha  
 +
** Crystals:
 +
**: - Received 70 crystals from SICCAS. 66 have been pre-selected by Jane's group
 +
**: - sent additional 4 (supposed to be from the previous batch). Quality of those crystals is very poor [https://halldweb.jlab.org/detectors/fcal2/crystals/delivered/SICCAS/bad_crystals.jpg][https://halldweb.jlab.org/detectors/fcal2/crystals/delivered/SICCAS/bad_crystals1.jpg]
 +
** Received 960 short signal cables [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/short_signal.jpg]
 +
** Procurement parts for the LMS:
 +
**: - Waiting for 7,600 ft of optical fibers (August/September)
 
* '''Module fabrication'''  -- Sasha   
 
* '''Module fabrication'''  -- Sasha   
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/module_fabrication/status/fcal_fabrication.pdf  Status of fabrication ] -->
 +
** All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
 
* '''Ongoing projects''' -- Sasha, all
 
* '''Ongoing projects''' -- Sasha, all
 +
** Visual inspections of fabricated modules [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/19_05_2023/modules_qa.docx] - done 
 +
** Prepare to move modules into Hall D [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move.jpg] [https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/move_to_halld/prepare_to_move2.jpg], wrap modules with sort towels. Need to move about 100 modules to the Hall.
 +
** Tested, labeled, and bundled all 100 (+ 2 spares) [https://halldweb.jlab.org/detectors/fcal2/installation/photos/label_signal/signal_bundles.jpg] signal cables connected from the flash ADC to the patch panel [https://halldweb.jlab.org/wiki/index.php/Testing_and_labeling_cables] - done
 +
** Test and label 960 short signal cables - ongoing
 +
** Tested fabricated modules using LMS [https://halldweb.jlab.org/wiki/index.php/Testing_ECAL_modules] - done  (need to update the wiki page)
 +
** Cutting optical fibers and gluing plastic caps [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/06_23_2023/glue_caps.jpg], waiting for 7600 ft of optical fibers
 +
** Work on refurbishing LG modules. About 60 modules have to be checked / fixed (rejected during installation)
 +
** [https://docs.google.com/presentation/d/1euIA49SszoQmSM4Lxu1OtZ8OfjltgwzXIbXo6TPEB3s/edit#slide=id.p Report from students]
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
 
* '''[[Testing of PMT dividers]]''' -- Sasha / Vlad
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Procedures]'''
+
** Received 10 dividers (first article) ! , going to test them during this week (Chris)
 +
* '''[https://halldweb.jlab.org/wiki/index.php/FCAL_Insert_Module_Fabrication Proceedures]'''
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob
 
* '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Arshak / Vlad / Hakob
 +
**  Detector installation [https://logbooks.jlab.org/book/halld][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/photos/install_fcal/students_detector.jpg]
 +
** [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 +
** Updates from the meetings with Tim's group [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Design_Meetings]
 +
** Discussion of the FCAL2 installation procedures [https://halldweb.jlab.org/wiki/index.php/FCAL_2_Installation_Meetings]
 +
** [https://halldweb.jlab.org/wiki/index.php/Distribution_of_signals_and_voltages Final mapping of low-voltage cables]
 +
** Mindy continues with wrapping crystals and soldering wires to sockets.
 +
** [https://halldweb.jlab.org/wiki/index.php/List_of_tasks_and_manpower Projects for summer students]
 +
** [https://halldweb.jlab.org/detectors/fcal2/installation/students_2023/list_of_students_2023.xlsx Summer Students (2023) ]
 +
<!-- ** [https://halldweb.jlab.org/detectors/fcal2/installation/photos Disassembling FCAL] -->
 
*'''Light monitoring system''' -- Arshak
 
*'''Light monitoring system''' -- Arshak

Revision as of 08:42, 25 August 2023

Meeting time and location:

Agenda

  • Preparation of parts for ECAL modules -- Sasha
    • Crystals:
      - Received 70 crystals from SICCAS. 66 have been pre-selected by Jane's group
      - sent additional 4 (supposed to be from the previous batch). Quality of those crystals is very poor [1][2]
    • Received 960 short signal cables [3]
    • Procurement parts for the LMS:
      - Waiting for 7,600 ft of optical fibers (August/September)
  • Module fabrication -- Sasha
    • All modules have been fabricated, checked, and inventorized (about 1610 modules in total)
  • Ongoing projects -- Sasha, all
    • Visual inspections of fabricated modules [4] - done
    • Prepare to move modules into Hall D [5] [6][7], wrap modules with sort towels. Need to move about 100 modules to the Hall.
    • Tested, labeled, and bundled all 100 (+ 2 spares) [8] signal cables connected from the flash ADC to the patch panel [9] - done
    • Test and label 960 short signal cables - ongoing
    • Tested fabricated modules using LMS [10] - done (need to update the wiki page)
    • Cutting optical fibers and gluing plastic caps [11], waiting for 7600 ft of optical fibers
    • Work on refurbishing LG modules. About 60 modules have to be checked / fixed (rejected during installation)
    • Report from students
  • Testing of PMT dividers -- Sasha / Vlad
    • Received 10 dividers (first article) ! , going to test them during this week (Chris)
  • Proceedures
  • Installation of the FCAL2 detector & integration to GlueX -- Sasha / Arshak / Vlad / Hakob
  • Light monitoring system -- Arshak